Environmental Impact Assessment (EIA) for the
Petitcodiac River Causeway Issues Tracking Log Summary of Comments, Correspondence, Releases
As of May 2, 2004
|
No. |
Date Received |
Comments (Summarized) |
| 1 |
28/06/2002 |
Disappointment with Draft Guidelines in describing review and consideration of Status Quo. Petitcodiac Riverkeeper will not take part in this or future assessments on river unless Provincial and Federal governments commit to making option 3 & 4 focus of EIA. Public consultations follow a suggested format. Must improve habitat and conditions for native fish. Socio-economic assessment must consider all future activities resulting from restoration. The role of the Greater Moncton District Planning Commission on the Technical Review Committee (TRC) should be evaluated. |
| 2 |
Unrecorded |
Provincial & Federal Governments must provide monetary commitment to project.
|
| 3 |
Unrecorded |
Restore the significant tidal bore along with andronomous fish spawning in the headwater.
|
| 4 |
Unrecorded |
Study mandate should include remediation of pollution from dump site, flooding of farmland, the Alma lobster fishery, etc.
|
| 5 |
Unrecorded |
Damage to river could and should be repaired.
|
| 6 |
Unrecorded |
Remove the causeway and build a bridge.
|
| 7 |
Unrecorded |
Thorough study of the issues needed. Fish passage must be improved.
|
| 8 |
Unrecorded |
Replace causeway with multiple span bridge. Leave small section of causeway to protect dump from erosion.
|
| 9 |
Unrecorded |
Keep Status Quo. Enjoys the fishing
|
| 10 |
Unrecorded |
Something needs to be done now, no need for more studies. Remove the causeway or at least open the gates.
|
| 11 |
Unrecorded |
Open gates and then perform EIA as river restores itself.
|
| 12 |
Unrecorded |
Beware of using existing reports in preparing a new report.
|
| 13 |
Unrecorded |
Leave causeway as is for another 25 years, may have answers and solution then.
|
| 14 |
Unrecorded |
Need to inform public on the issues.
|
| 15 |
Unrecorded |
Restore fish passage for all species.
|
| 16 |
Unrecorded |
Remove causeway and restore river to natural state.
|
| 17 |
Unrecorded |
Of the four options, replacing a portion of the causeway with a bridge is the best. Status quo is unacceptable. How will fish species migration be identified so the gates may be opened for all species?
|
| 18 |
Unrecorded |
Questioning Federal and Provincial commitment to resolve identified issues. Issues raised on negative impacts on property, industry, recreation and wildlife. Redesigning fishway appears to be strong option. Mandate of EIA team limited. Should focus on action plan to restore ecological health of Petitcodiac River system. Seems to be strong public support to remove causeway. Concerns with former dump site affecting water quality addressed.
|
| 19 |
25/01/2003 |
Study should be presented to public through government. It should be necessary to study history of the river to understand the effects of siltation. New study boundaries for Terms of Reference (TOR) to be considered. Take in account ice melt in Antarctica causing increased ocean elevation during modeling phase.
|
| 20 |
28/01/2003 |
River will not return to previous state if causeway removed. May lead to increased erosion along south side Salisbury Rd. Existing flooding above causeway should be addressed if causeway remains. Unused marsh land set aside for wildlife preserves. Dredging program used to control silt below causeway. Enjoys living near headpond.
|
| 21 |
28/01/2003 |
Petitcodiac Riverkeeper to abandon EIA process if no commitment to follow through by Provincial and Federal governments after study is completed.
|
| 22 |
29/01/2003 |
Must not overlook the impacts on the upstream portion of the Petitcodiac River.
|
| 23 |
30/01/2003 |
Need to reduce the risk of flooding following major storms. Siltation exacerbates flooding. Erosion along river, above and below gates needs to be addressed.
|
| 24 |
30/01/2003 |
Concerned with negative effects from federal legal interventions.
|
| 25 |
31/01/2003 |
Support river being opened as much as possible. Options other than the Niles options to be presented. Concerned about lack of direction from Province.
|
| 26 |
03/02/2003 |
Pointed out in the stakeholders list, Port Elgin may have been confused with Elgin, the Local Service District.
|
| 27 |
05/02/2003 |
Should include cost of civic pride in total cost accounting. Existing dump site needs to be addressed before it is disturbed. Suggested a vote by all stakeholders to aid in outcome.
|
| 28 |
06/02/2003 |
Discussions concerning pervious correspondence.
|
| 29 |
07/02/2003 |
Must let people know that there are no salmon in the Bay of Fundy and other rivers and no simple action will fix this. Must ensure a complete and honest EIA process.
|
| 30 |
07/02/2003 |
Construct new dam, spillway and fish passage to work with existing tidal conditions.
|
| 31 |
12/02/2003 |
Remove Causeway and let river return to natural state.
|
| 32 |
13/02/2003 |
It is time for a scientific review of the proposed causeway options. Public consultation has been overdone. Computerized modelling of the river necessary. Consultation with special interest groups carried out by Consultant. Information made available to public. The study review panel be truly independent. Government ministers be responsible for quality of study.
|
| 33 |
14/02/2003 |
General e-mail sent out to club members containing information on Moncton Public Meetings and how to obtain and forward comment forms.
|
| 34 |
17/02/2003 |
Opening gates will create mudflats in headpond area, could destroy wildlife, will be unsightly and possibly cause air pollution.
|
| 35 |
17/02/2003 |
Review effect of opening causeway on local sewage lagoons, how fish passage is handled at Beechwood dam, Turtle Creek reservoir blocking fish passage, using Petitcodiac headpond as a water source for the City.
|
| 36 |
18/02/2003 |
Public must realize "Restoration" will not be as the word implies. Bank erosion protection will be needed if any of the four options chosen. Concerned with outflow from dump site. A high-tech fishway appears to be least destructive and expensive option. Provincial and Federal governments making separate final decisions could be potential problem. Caution to be wary of media.
|
| 37 |
18/02/2003 |
Minutes of meeting between AMEC Study Team and Petitcodiac Riverkeeper, held on Feb. 12, 2003. Existing landfill needs to be addressed. Executive Summary at end of study must address magnitude of impact on river and community. Benefits of restoration need to be documented. Tidal bore as a tourist attraction. Who are the stakeholders? Restoration for Petitcodiac Riverkeeper means unimpeded fish passage. Is a bridge an option. EIA should include ecological, social & economic components. Should Memramcook River causeway be included in study? Petitcodiac Riverkeeper concerned with Moncton District Planning Commission is a part of TRC. What will be effects on agricultural lands?
|
| 38 |
19/02/2003 |
Causeway should not have been built, replace with bridge.
|
| 39 |
19/02/2003 |
Causeway should not have been built, restore river.
|
| 40 |
23/02/2003 |
Open gates to restore fish habitats and stop silt accumulation in Dover area.
|
| 41 |
21/02/2003 |
Discussions concerning a proposed redesigned fishway.
|
| 42 |
25/02/2003 |
Salt intrusion into groundwater wells if causeway removed. Causeway controls flooding and erosion up river. Fishing in headpond nets bass, sea trout, pickerel and gaspereau.
|
| 43 |
25/02/2003 |
Discussions concerning a proposed redesigned fishway.
|
| 44 |
26/02/2003 |
Discussions and inquiries into EIA risks and mitigation of risk, legal matters, due diligence. Points out landfill poses unacceptable risk to river ecosystem.
|
| 45 |
27/02/2003 |
Contact for Fort Folly Habitat Recovery Program.
|
| 46 |
27/02/2003 |
Concerned with pollution in river system. Need to assess methods of stocking rivers with fish. What is the silt load coming in with the tides?
|
| 47 |
28/02/2003 |
Petitcodiac Riverkeepers leaving EIA process because no commitments received from Governments. Reiterated that: component results to be cross-examined by stakeholders, need for causeway gates openings to give credibility to modelling exercise, review timeframe in order to allow credible modeling information.
|
| 48 |
28/02/2003 |
Supports partial bridge option. Must be careful not to over-emphasize certain consequential economic activities. Government to replace dyke systems.
|
| 49 |
28/02/2003 |
Believe consultants can not rely on what public perceives as being fish passage. Wants assurance that action will be taken once the report is submitted in 2005.
|
| 50 |
03/03/2003 |
Why are the options limited to those presented. The goal should be to restore the Petitcodiac River to a fully functioning ecosystem. Commercial fishing should include socioeconomic considerations. List of stakeholders is limited. Should have a limnologist, an ornithologist or a salt marsh specialist involved in study. Study to include salt marshes. "Valued Environmental Components" should include all components whether or not valued by humans.
|
| 51 |
10/03/2003 |
Would like to attend Aquatic workshop with a proposed modification to fishway.
|
| 52 |
26/04/2003 |
Construction of ship berths in area of Champlain Place to be considered.
|
| 53 |
26/04/2003 |
Was there any dredging completed on the Petitcodiac River?
|
| 54 |
26/04/2003 |
How is odour measured?
|
| 55 |
26/04/2003 |
Avon River Causeway in Windsor N.S. : Data available that may be useful to the AMEC Study Team for this EIA study.
|
| 56 |
26/04/2003 |
How is noise measured with respect to exposure of the people living near the river?
|
| 57 |
26/04/2003 |
What elements is the AMEC Study Team looking at with regards to air quality?
|
| 58 |
26/04/2003 |
Indoor air quality will not be addressed in this EIA study.
|
| 59 |
26/04/2003 |
Increased flooding is currently affecting air quality inside buildings. Is the AMEC Study Team going to address this item under the cumulative effects component of the EIA study?
|
| 60 |
26/04/2003 |
Will flooding be assessed for each option?
|
| 61 |
26/04/2003 |
Define direct and indirect mortality.
|
| 62 |
26/04/2003 |
How will the AMEC Study Team measure morbidity?
|
| 63 |
26/04/2003 |
Extend the field investigation beyond Shepody, Memramcook, Chignecto Bay. Is there a summary of the field investigation for the stakeholders, public and aboriginal community to review?
|
| 64 |
26/04/2003 |
Will the AMEC Team assess the status quo on the Halls Creek area?
|
| 65 |
26/04/2003 |
Will water sampling be completed on the headpond in the winter months?
|
| 66 |
26/04/2003 |
Will the mosquito control issue in the wetland be addressed?
|
| 67 |
26/04/2003 |
Will mudflats that exist today always be there?
|
| 68 |
26/04/2003 |
Pre-causeway: Geese migration in Halls Creek area; Will historical information also be reviewed?
|
| 69 |
26/04/2003 |
Trial gate experiments provides significant amount of information upstream of the Causeway. Is the AMEC Study Team going to carry out additional trial gate openings for the modelling?
|
| 70 |
26/04/2003 |
Is the AMEC Study Team investigating the areas along the river where there is extensive sedimentation?
|
| 71 |
26/04/2003 |
Identify borehole locations and field investigation on website.
|
| 72 |
26/04/2003 |
Johnson's Point: Change in mudshrimp population; Recommend boreholes at Johnson's Mills and Mary's Point be completed.
|
| 73 |
26/04/2003 |
Will erosion be studied when the Tidal Bore is arriving?
|
| 74 |
26/04/2003 |
Tidal Bore to be evaluated on a more complex model.
|
| 75 |
26/04/2003 |
Where does primary treated sewage system go when Tidal Bore arrives?
|
| 76 |
26/04/2003 |
When will secondary sewage treatment be assessed?
|
| 77 |
26/04/2003 |
UNB and Acadia are doing work on mudflat productivity.
|
| 78 |
26/04/2003 |
Value of sport bass fishery to be established.
|
| 79 |
26/04/2003 |
Shad (fishing done by drift nets), commercial fishery will also be evaluated.
|
| 80 |
26/04/2003 |
The Department of Fisheries and Oceans (DFO) put restriction on scallop fishery to avoid overfishing.
|
| 81 |
26/04/2003 |
Productive scallop fishery in Chignecto Bay.
|
| 82 |
26/04/2003 |
Modelling: How much sediment will be displaced with gate(s) opening or partial bridge installation?
|
| 83 |
26/04/2003 |
Turtles have been known to lay eggs in the Turtle Creek area. Will the snapping or wood turtles be considered in Full Cost Accounting (FCA)?
|
| 84 |
26/04/2003 |
Can smolts migrate through the headpond?
|
| 85 |
26/04/2003 |
Explain DFO's gate management plan and if it is working?
|
| 86 |
26/04/2003 |
Will Memramcook Causeway only be addressed by cumulative effects?
|
| 87 |
26/04/2003 |
Is the AMEC Study Team analysing the benthic community in the lobster fishery area and determining why there is an increase in the lobster fishery?
|
| 88 |
26/04/2003 |
Is the fish population declining due to the causeway, acid rain, spruce budworm spraying, etc.?
|
| 89 |
31/05/2003 |
General comments made during workshop are as follows: The wording of the TOR be revised to eliminate perceived biases. The definition of municipal services should include public and private infrastructure. The TOR should be more specific as to follow what is actually being done in the EIA. Potential refunds to non-profit organizations that spent money on previous studies, if results are used in EIA.
|
| 90 |
31/05/2003 |
Land Use & Value items indicated during workshop are as follows: Environmental effects on land use and value up and downstream of causeway. Assessment not limited to waterfront properties. The Petitcodiac River Watershed should be compared to similar watershed. Current value of lost agricultural land should be evaluated. Need to include the intangible aspects of land valuation. All dumps along river and tributaries will have environmental effects. Pre-causeway state to be used as baseline for aesthetic issues and their environmental effects on land value.
|
| 91 |
31/05/2003 |
Labour & Economy items indicated during workshop are as follows: The assessment must include all positive and negative economic environmental effects associated with all socio-economic components. All jobs, before and after, need to be assessed. All stakeholders must be included in the study.
|
| 92 |
31/05/2003 |
Municipal Services & Infrastructure items indicated during workshop are as follows: Current state of dykes and aboiteaux and land adjacent to river, up and downstream of causeway must be identified and used as status quo. Authorities responsible for dykeland protection, restoration and maintenance payment to be identified before choosing option. Sediment and erosion up and downstream to be addressed. Selected project option causing flow augmentation could cause flooding. Potential loss of farmland to be addressed. Ownership of land created along riverbed to be addressed. Issues related to Tower Road Dam on Turtle Creek.
|
| 93 |
31/05/2003 |
Transportation Network items indicated during workshop are as follows: Continuation of emergency services during construction phase. Traffic congestion created during causeway closure and solutions to alleviate such traffic issues. The new Petitcodiac River Bridge and approach ramps to be constructed before construction of selected option.
|
| 94 |
31/05/2003 |
Vessel Traffic & Navigation items indicated during workshop are as follows: pre-causeway vessel traffic used as status quo for assessment. Sedimentation may have been issue even if causeway not constructed. Boating activities may cause erosion. Current and future trends in boating and river recreation to be examined. Recreational and commercial uses of river before and after causeway construction. Vessel navigation prior to causeway. Major public events on river. Bridge option should follow Coast Guard Regulations for bridge height.
|
| 95 |
31/05/2003 |
Tourism & Recreation items indicated during workshop are as follows: Pre-causeway status and value of tourism. Balance between development and habitat conservation. For many years there has been no recreational boating on Petitcodiac River. Outhouse Point has more effect on Tidal Bore than causeway. Tidal Bore and salmon fishery tourism existed prior to causeway. Float planes, commercial tourism and tourist destinations are potential tourism activities. Walking trails around Ducks Unlimited property. Potential to increase use of existing facilities and current activities. Construct tourist information center near causeway. Shepody Bay lobster boat tours and possibly shark fishing. Alma region kayaking and canoeing. Bird watching potential may be exploited. Tourism ventures that have been developed since causeway construction. Winter activities developed since causeway construction. Supportive infrastructure must be set in place for headpond tourism ventures to succeed. Will headpond fill in if causeway is kept. Effect of sediment transport on Dorchestor Sandpiper Festival.
|
| 96 |
31/05/2003 |
Archaeology & Heritage Resources items indicated during workshop are as follows: There are archaeological sites along Memramcook River and other tributaries. Memramcook dykelands and aboiteaux are of significant cultural and historical relevance. All archaeology of the area must be characterized to determine effects of sedimentation and deposition. Potential effects of options on archaeological site above causeway. No archaeological surveys completed along shoreline of river. Access to EIA historical and archaeological information to anyone. Promote archaeological sites for tourism. Not too many known archaeological sites on river system. In order to capture river heritage, necessary to tell story of river prior to causeway. Card Pazant in Dorchester is a potential interpretative site for reconstructing a 18th century boat and restoration of the area's boat building heritage.
|
| 97 |
31/05/2003 |
Public Health & Safety items indicated during workshop are as follows: Quantity and Quality of water up and downstream of causeway. Environmental effects of dumps in watershed. Fish eating from contaminated river bottom. Implementation of immediate and future prevention measures before any causeway modifications. Microclimatic changes pre & post causeway construction, and potential changes that may occur with selected option. Potential increase of traffic accidents during construction of the option. Effluent discharge, both public and private, up and downstream of causeway may differ between options and times of year. Effluent flows into headpond could increase BOD and COD. Combination of Turtle Creek Dam and headpond level control could cause increased flooding risk. Disruptions of emergency services during construction. Tourism development may cause more traffic problems and increased noise pollution. Existing water quality and characteristics. Safe access to headpond and river for emergency vehicles. Emergency Measures Organization (EMO) plan to access headpond and river. Effects of water level on insect populations.
COD: Chemical Oxygen Demand BOD:Biological Oxygen Demand
|
| 98 |
25/09/2003 |
Consider future generations and what is best for the Petitcodiac River when you reach your decision.
|
| 99 |
25/09/2003 |
Function of the existing fish ladder and its suitability to allow passage for all species.
|
| 100 |
25/09/2003 |
Population and diversity of native and invasive fish species in the Petitcodiac River and the headpond, before and after the construction of the Causeway.
|
| 101 |
25/09/2003 |
Health of fish and aquatic organisms and the potential impacts of the landfill site and the sewage treatment plant.
|
| 102 |
25/09/2003 |
Commercial fishing and recreational angling activity.
|
| 103 |
25/09/2003 |
Field investigations related to lobster fishing in the Alma area.
|
| 104 |
25/09/2003 |
Function, development and health of the wetlands as well as the population and diversity of native and invasive plants and animals.
|
| 105 |
25/09/2003 |
Agriculture land and farming activities.
|
| 106 |
25/09/2003 |
Potential to include the Shepody, Memramcook and Mill Creek dams in the EIA study.
|
| 107 |
25/09/2003 |
Develop a tourist information centre and tidal bore lookout in Lower Coverdale to maximize views of the tidal bore and offer interpretation on the causeway, Petitcodiac River/Estuary, landfill site, sewage treatment plant. etc.
|
| 108 |
25/09/2003 |
Investigate the fishway in Grand Falls, Newfoundland & Labrador and interview the facility manager.
|
| 109 |
25/09/2003 |
Is there a fishway design that will accommodate all fish species in the Petitcodiac River?
|
| 110 |
25/09/2003 |
Study schedule, progress of various phases, upcoming events and future open house locations.
|
| 111 |
25/09/2003 |
Opportunity for public review of all EIA study documents and the length of time required for the government to proceed with the recommended project option.
|
| 112 |
25/09/2003 |
Timing of the final decision and opportunities for the public and stakeholders to be involved.
|
| 113 |
25/09/2003 |
Length of time required for the River to be restored to its original state if the causeway is removed.
|
| 114 |
25/09/2003 |
Impact of climate change and incorporation into the modelling process - the water level in the Petitcodiac River is higher today than 5 years ago. In the past 5 years the Petitcodiac River watershed has been subject to more storms, higher winds, higher tides and flooding.
|
| 115 |
11/11/2003 |
What do you refer to as headpond? Comment on calling the lake a headpond and impoundment.
|
| 116 |
11/11/2003 |
Do you need a fishing license when fishing in the headpond?
|
| 117 |
11/11/2003 |
If the causeway is taken out will there be silt all the way to Salisbury?
|
| 118 |
11/11/2003 |
Regarding the slide of 1945. There is no causeway. The Bridge is in place. Did the silt showing in picture come up the river? Where did silt come from?
|
| 119 |
11/11/2003 |
You have age photos of headpond. Are they doing other age photos of other rivers?
|
| 120 |
11/11/2003 |
What year did they stop dredging on the River?
|
| 121 |
11/11/2003 |
Regarding Salt marshes. Are you looking at this?
|
| 122 |
11/11/2003 |
Why is it that before the causeway was built, boats could not go up river because of silt buildup?
|
| 123 |
11/11/2003 |
Would the headpond fill in if causeway is taken out?
|
| 124 |
11/11/2003 |
In 1861 photo and present day photo, large amounts of mudflats can be seen above and below. They are almost identical. Before and after the causeway, nothing has changed. How do you explain this?
|
| 125 |
11/11/2003 |
What about the fresh water clams? Millions of clams were killed when the causeway was opened and rare ones were also found at that time. What is being done about this?
|
| 126 |
11/11/2003 |
Dept of Fisheries has played with smolts for years. . It would be interesting if salmon were introduced with transmitters.
|
| 127 |
11/11/2003 |
Were the fish successful in getting into the headpond? How are you finding the health of the fish?
|
| 128 |
11/11/2003 |
You say that everything is on schedule. When will we get results of this assessment?
|
| 129 |
11/11/2003 |
Who is responsible potentially for the concerns of the Riverview Marina?
|
| 130 |
11/11/2003 |
Water is so high at times that erosion on the banks has taken place. They should let water out at causeway when needed.
|
| 131 |
16/01/2004 |
The AMEC Study team should investigate the fish passage facility on the Fraser River in British Columbia.
|
| 132 |
16/01/2004 |
Are the fish today dieing as a result of the river silt clogging the fish gills while they are swimming in the Petitcodiac River.
|
| 133 |
16/01/2004 |
Is the Memramcook Causeway included in the EIA study terms of reference.
|
| 134 |
16/01/2004 |
Supporting river restoration and would prefer to see a bridge constructed and the causeway removed; “ take the causeway out and let nature take care of itself.”
|
| 135 |
19/01/2004 |
Who is responsible for the Petitcodiac River Causeway infrastructure?
|
| 136 |
19/01/2004 |
Is the existing infrastructure being evaluated during the PRC EIA?
|
| 137 |
19/01/2004 |
Does the current fishway work?
|
| 138 |
19/01/2004 |
Is the status quo an option? Why is the status quo used as a baseline condition and not an option?
|
| 139 |
19/01/2004 |
How many stakeholders are currently involved in the PRC EIA?
|
| 140 |
19/01/2004 |
How often do we meet with the stakeholders?
|
| 141 |
19/01/2004 |
Will the PRC EIA be completed on schedule?
|
| 142 |
19/01/2004 |
Will fish passage, other ecosystems and the silting river be addressed after the PRC EIA is completed?
|
| 143 |
19/01/2004 |
Is the study addressing some of the current flooding challenges in Moncton and Dieppe?
|
| 144 |
19/01/2004 |
When will the “ultimate decision” be made? Is there a guarantee that in fact something will be done about the causeway and the study recommendations implemented? Where will the money come from?
|
| 145 |
16/02/2004 |
Will the AMEC study team estimate a cost for each option?
|
| 146 |
16/02/2004 |
Are any of the project options currently being favored?
|
| 147 |
16/02/2004 |
How many studies have been completed on the Petitcodiac River?
|
| 148 |
16/02/2004 |
Has the AMEC study team reviewed previous studies on the Petitcodiac River and will this information assist the EIA study?
|
| 149 |
16/02/2004 |
What is different about this study compared to the 100 plus studies completed on the Petitcodiac River?
|
| 150 |
16/02/2004 |
Did previous studies concentrate on any of the project options the AMEC study team is currently reviewing?
|
| 151 |
16/02/2004 |
How can an EIA study be done given the natural condition of the river and the tidal conditions?
|
| 152 |
16/02/2004 |
What factors would the AMEC study team look at if a bridge is installed versus a causeway?
|
| 153 |
16/02/2004 |
Is the study team looking at the role of the natural river as to how it filters water as well as the planetary supply of water?
|
| 154 |
16/02/2004 |
Do we understand the role the Petitcodiac River plays in its natural environment or state as far as nature is concerned?
|
| 155 |
16/02/2004 |
Do you anticipate it might be necessary for human intervention (i.e.,dredging) to permit the river to return to its natural state and enhance fish passage and improve other ecosystems?
|
| 156 |
16/02/2004 |
Would the river be left to restore itself naturally?
|
| 157 |
16/02/2004 |
How does the total suspended solids (TSS) in the Petitcodiac River compare to other tidal rivers and why is the TSS level so high? A comparison of TSS levels should only be with tidal rivers. How does the sediment concentration in the Petitcodiac River compare to the Shubenacadie?
|
| 158 |
16/02/2004 |
Is the high TSS levels due to the causeway construction or because the Petitcodiac River is a tidal river or a combination of both?
|
| 159 |
16/02/2004 |
Was there testing completed prior to the causeway construction to determine the TSS levels?
|
| 160 |
16/02/2004 |
How many test sites were completed by the AMEC study team and what is the broad area of the field investigation for this study?
|
| 161 |
16/02/2004 |
Where was the photo taken on the Petitcodiac River estuary indicating the layers of silt for each tidal cycle?
|
| 162 |
16/02/2004 |
How did the Petitcodiac River change since the causeway construction?
|
| 163 |
16/02/2004 |
Will the modelling indicate if the river will be restored to its original state prior to the construction of the causeway?
|
| 164 |
16/02/2004 |
Is the status quo an option? Is there a possibility we complete this EIA study, spend a lot of money to do the study and nothing will be done with the status quo?
|
| 165 |
16/02/2004 |
If fish passage is a primary concern, is it possible that the status quo could be an option?
|
| 166 |
16/02/2004 |
Were the majority of the concerns identified in the presentation related to a specific option?
|
| 167 |
16/02/2004 |
Will there be a cost associated with each of the major concerns?
|
| 168 |
16/02/2004 |
Would the cost associated with the impact on the abandoned landfill, if the causeway was open to free flow, be considered?
|
| 169 |
16/02/2004 |
Will the EIA report be based just on the science?
|
| 170 |
16/02/2004 |
Is an EIA being completed on each option?
|
| 171 |
16/02/2004 |
Can the public still ask questions on the EIA Study?
|
| 172 |
16/02/2004 |
Will there be some results released prior to the final report in 2005 indicating if one or more options will not be considered?
|
| 173 |
16/02/2004 |
Will the draft 2004 report identify which option is recommended and rank the options?
|
| 174 |
16/03/2004 |
Why was the causeway constructed? |
| 175 |
16/03/2004 |
Are the gates open all the time? |
| 176 |
16/03/2004 |
During construction of the causeway, did people realize there was a problem with sedimentation in the river? |
| 177 |
16/03/2004 |
It only took a year or so to notice the change in the sedimentation of the river after the causeway construction. |
| 178 |
16/03/2004 |
Currently, are there still many species of fish in the river? Even with all the sedimentation? |
| 179 |
16/03/2004 |
What is the role of this EIA compared to all the other hundreds of studies already completed on the Petitcodiac River? |
| 180 |
16/03/2004 |
Where do all the sediments come from? Has the sediment always been in the river and prior to the causeway construction? |
| 181 |
16/03/2004 |
Has the AMEC Study Team considered the opinion of the people living above the causeway on the headpond? |
| 182 |
16/03/2004 |
Will the headpond eventually fill in with sediment? When? |
| 183 |
16/03/2004 |
Has the AMEC Study Team completed real simulations/modelling of the various options? In what time period is the modelling completed? |
| 184 |
16/03/2004 |
With all the cost of all the studies completed on the Petitcodiac River we could have constructed a bridge versus a causeway. |
| 185 |
16/03/2004 |
Will a bridge ever be constructed? |
| 186 |
16/03/2004 |
If the causeway gates were open, would the bass fishery in the headpond be affected? |
| 187 |
16/03/2004 |
The causeway has stopped the energy of the tidal bore in the river and caused the silt to deposit in the Petitcodiac river. |
| 188 |
16/03/2004 |
If a bridge was constructed how fast would the river be restored? |
| 189 |
17/04/2004 |
Elaborate on what signal fish require to locate a certain river to spawn, i.e. Pollett, Little and North Rivers. Is it smell, taste?
|
| 190 |
17/04/2004 |
Shad go from Florida to the Gulf of St. Lawrence, how do they know where to come back? Do fish follow the stars and magnetic north? Is it smell?
|
| 191 |
17/04/2004 |
Do fish respond to taste, smell and geology of the river?
|
| 192 |
17/04/2004 |
Do fish respond to rainfall? |
| 193 |
17/04/2004 |
What happens when there is low rainfall amount in July and August when flows are low in the Petitcodiac River?
|
| 194 |
17/04/2004 |
Explain the importance of the oxygen level to the fish and what is the lowest level they can tolerate.
|
| 195 |
17/04/2004 |
Please provide examples of low levels of oxygen in the Petitcodiac Rver. |
| 196 |
17/04/2004 |
How does the saturation level effect the fish? How is saturation level and oxygen level related? Please explain that.
|
| 197 |
17/04/2004 |
How do fish react to the abrupt change from salt to fresh water sometimes experienced downstream of the causeway?
|
| 198 |
17/04/2004 |
What oxygen level and satuation level is good for fish? |
| 199 |
17/04/2004 |
What is causing the stress, low oxyen levels in the headpond? i.e. Outhouse Point runoff, fertilizer?
|
| 200 |
17/04/2004 |
We have a dump and sewage treatment plant. What effect do these have on the oxygen level? |
| 201 |
17/04/2004 |
Where were the low oxygen results found? Is it possible to have a copy of the results and the field investigation results?
|
| 202 |
17/04/2004 |
Does the fertilizer from farms or the sewage treatment plant affect the fish taste characteristic? |
| 203 |
17/04/2004 |
What is the oxygen and saturation levels in the river and the headpond? Is it different around the sewage treatment plant? Did you collect data below the causeway?
|
| 204 |
17/04/2004 |
Do the fish spawn in other rivers or do they spawn at all if they cannot locate fresh water? |
| 205 |
17/04/2004 |
What percentage of the fish population drift to other locations? |
| 206 |
17/04/2004 |
How much does it cost to dredge Cardiff Wales twice a year? |
| 207 |
17/04/2004 |
Where is the fishway in Cardiff Wales situated compared to the original head of tide? |
| 208 |
17/04/2004 |
How does the sediment concentration at Cardiff Wales compare to the Petitcodiac River? |
| 209 |
17/04/2004 |
Where was the original river located at Cardiff Wales? What is the river like? |
| 210 |
17/04/2004 |
Is the Cardiff Wales headpond level lower than the head of tide? |
| 211 |
17/04/2004 |
Will there ever be a need to dredge the Cardiff Wales headpond? |
| 212 |
17/04/2004 |
Is the aeration pipes located under the entire Cardiff Wales headpond? Could you explain this system?
|
| 213 |
17/04/2004 |
How often is the oxygen level in the Cardiff Wales headpond monitored? |
| 214 |
17/04/2004 |
Please confirm the size of the berm or barrage at Cardiff Wales? |
| 215 |
17/04/2004 |
Please confirm if the purpose of the dredging at Cardiff Wales is for fish passage or ships? |
| 216 |
17/04/2004 |
How important is the water temperature in the headpond and estuary at Cardiff Wales? |
| 217 |
17/04/2004 |
Please confirm the total cost of the Cardiff Wales project. |
| 218 |
17/04/2004 |
Please confirm the type of recreation activities on the Cardiff Wales headpond? Do they use the headpond for swimming?
|
| 219 |
17/04/2004 |
How does the Cardiff Wales winter conditions compare to the Petitcodiac River winter conditions? |
| 220 |
17/04/2004 |
Does the Cardiff Wales facility have to deal with ice conditions? |
| 221 |
17/04/2004 |
How does the weather conditions and temperatures in Cardiff Wales compare to New Brunswick? |
| 222 |
17/04/2004 |
How long did it take to construct Cardiff Wales? |
| 223 |
17/04/2004 |
Why could they not want to let the salt water into the Cardiff Wales freshwater headpond? |
| 224 |
17/04/2004 |
Please confirm if predators, for example birds, is an issue for the Cardiff Wales fish passage facility?
|
| 225 |
17/04/2004 |
Were there any cormorants around the salt and/or fresh water at Cardiff Wales? |
| 226 |
17/04/2004 |
Are there any fish species that are only found in the Petitcodiac River? |
| 227 |
17/04/2004 |
Is there any historical records indicating how many fish were in the Petitcodiac River precauseway? |
| 228 |
17/04/2004 |
Why do we have such a high total suspended sediments in the Petitcodiac River? |
| 229 |
17/04/2004 |
Can kelts re-acclimate in saltwater where salt water is found immediately downstream of causeway? |
| 230 |
17/04/2004 |
Are there any other fish species in the Petitcodiac River that are not listed? |
| 231 |
17/04/2004 |
If the Petitcodiac River is not available for fish to spawn what other rivers are available in the Bay of Fundy watershed?
|
| 232 |
17/04/2004 |
What percentage does the Petitcodiac River make up of all the other rivers in the Bay of Fundy watershed?
|
| 233 |
17/04/2004 |
What percentage of the productive fish habitat of the area is found in the Petitcodiac river? |
| 234 |
17/04/2004 |
Has the AMEC Study Team investigated the Avon River Causeway in Windsor N.S. and the Shubenacadie River regarding fish passage ?
|
| 235 |
17/04/2004 |
Are the stop logs in place at the Petitcodiac River Causeway? |
| 236 |
17/04/2004 |
Are the stop logs used in the current gate management plan? |
| 237 |
17/04/2004 |
How did the AMEC Study Team lose some of the smolts? |
| 238 |
17/04/2004 |
Did the AMEC Study Team actively monitor the smolts? |
| 239 |
17/04/2004 |
What is a pregrilse? Is it some kind of "supersmolt"? |
| 240 |
17/04/2004 |
What is the life expectancy of the battery of the tags placed in the smolts? |
| 241 |
17/04/2004 |
Why did DFO place pregrilse in the headpond? What was the purpose? |
| 242 |
17/04/2004 |
Did the AMEC Study Team recover any of the tagged pregrilse? |
| 243 |
17/04/2004 |
How does the pregrilse relate to the EIA Study fieldwork? |
| 244 |
17/04/2004 |
Can shad pass the Petitcodiac River Causeway fishway? |
| 245 |
17/04/2004 |
Can sturgeon or smelt pass the Petitcodiac River Causeway fishway at low flow? |
| 246 |
17/04/2004 |
Did AMEC Study Team modify the exisiting fish trap or line the fish trap? |
| 247 |
17/04/2004 |
Where was the water samples taken in the headpond in the winter? |
| 248 |
17/04/2004 |
Please confirm what species did you find in the headpond? |
| 249 |
17/04/2004 |
Where were the water temperatures taken in estuary? |
| 250 |
17/04/2004 |
What is the objective of the gate management plan with regards to maintaining the headpond level and mud accumulation? Why is the headpond level maintained at 6.1 metres?
|
| 251 |
17/04/2004 |
How much did the salmon sport fishery declined after the causeway construction? Is the AMEC Study Team going to refer to the 1990 DFO paper that attributed the loss of stocks to the causeway?
|
| 252 |
17/04/2004 |
Did the Atlantic Salmon go to the Shubenacadie River since the Petitcodiac River Causeway was installed?
|
| 253 |
17/04/2004 |
Has the AMEC Study Team taken into acount the sewage treatment plant and its effect on the fish? |
| 254 |
17/04/2004 |
Has water sampling been completed at Outhouse Point and in the headpond? |
| 255 |
17/04/2004 |
Did the AMEC Study Team find any historical information on thresher sharks? |
| 256 |
17/04/2004 |
What is the water quality in the headpond? |
| 257 |
17/04/2004 |
How did the AMEC Study Team investigate the health of the fish below the causeway? |
| 258 |
17/04/2004 |
What about the pollution in the river due to the Sewage Treatment plant? |
| 259 |
17/04/2004 |
I believe the Big Salmon River is in Fundy National Park. The salmon catch has dropped in this river since 1985. This river is stocked frequently.
|
| 260 |
17/04/2004 |
The Gunningsville Bridge is very close to the Hawkes Road. Why is the salinity low at the Gunningsville Bridge?
|
| 261 |
17/04/2004 |
Is the EIA Study based on the Fisheries Act? |
| 262 |
17/04/2004 |
There is concern about the negative impact the landfill sites and the sewage treatment plant have on fish. The causeway has also caused an impact on the fish.
|
| 263 |
17/04/2004 |
Today we have explored many fishways, however, can we construct a fishway in the Petitcodiac River that would work under the conditions we have in the river?
|
| 264 |
17/04/2004 |
Can we eliminate the silt in the river? |
| 265 |
17/04/2004 |
Can the gate management plan be modified to enhance fish passage? |
| 266 |
17/04/2004 |
Trapping and transport of fish species would only work for Atlantic salmon. Is this correct? |
| 267 |
17/04/2004 |
Can options 1 and 2 now be dropped? |
| 268 |
17/04/2004 |
Fish passage was not an issue prior to the causeway construction. |
| 269 |
17/04/2004 |
Does the AMEC Study Team know if fish passage would be a problem if the causeway gates are to open? Will the fish return?
|
| 270 |
17/04/2004 |
Does the AMEC Study Team have any other information on the river? |
| 271 |
17/04/2004 |
There is very little fish movement in July and August. Is the fish migration really affected by not opening the gates in the summer and winter?
|
| 272 |
17/04/2004 |
What are the results of DFO stocking the river? |
| 273 |
17/04/2004 |
The Petitcodiac River has not changed much since the causeway was constructed? |
| 274 |
17/04/2004 |
Aerial photos do not indicated a change in the river since the causeway was constructed. |
| 275 |
17/04/2004 |
How does the AMEC Study Team know the fish are not successfully migrating downstream if the fish are not counted?
|
| 276 |
17/04/2004 |
Do fish migrate year around? |
| 277 |
17/04/2004 |
What is the change in fresh water volume since the causeway construction? |
| 278 |
17/04/2004 |
Will there be larger deposits of sediment in the headpond when the causeway gates are open? |
| 279 |
17/04/2004 |
Will the sediment move into the headpond if all 5 gates are open? |
| 280 |
17/04/2004 |
What is the cause of the dramatic change in the flow of the water? |
| 281 |
15/06/2004 |
The importance of headpond as an emergency water supply for fire fighting should be considered. |
| 282 |
15/06/2004 |
Will the EIA report include Full Cost Accounting on tourism, recreation, decrease in property value, wildlife, freshwater value for fire fighting, sailing, and bass fishing tournaments, etc. if the headpond is eliminated?
|
| 283 |
15/06/2004 |
Is the AMEC Study Team going to assess the cost and benefits of all the Project Options and the Status Quo for the next 20 years?
|
| 284 |
15/06/2004 |
The AMEC Study Team should address all the concerns of the communities in the Petitcodiac River Watershed and include the cost of secondary sewage treatment facility and erosion protection for the landfill sites.
|
| 285 |
15/06/2004 |
The AMEC Study Team must complete an extensive effort and research on other fish passage methods in other jurisdictions and look into innovative ways to address the problem. All suggestions submitted by the public and stakeholder groups should be investigated.
|
| 286 |
15/06/2004 |
The AMEC Study Team must complete a good inventory of the fish species currently in the Petitcodiac River and predict the species there could be in the future under the status quo and the four project options.
|
| 287 |
15/06/2004 |
What would happen if there were two different decisions at the end of the PRC EIA from the Federal and Provincial Government?
|
| 288 |
15/06/2004 |
Did the AMEC Study Team research the other rivers that flow into the Bay of Fundy from the perspective of analyzing incremental changes that have occurred under different scenarios related to natural and anthropogenic obstacles and enhancements? How have these affected salmon?
|
| 289 |
15/06/2004 |
Current salmon issues are mostly related to aquaculture in the Bay of Fundy. |
| 290 |
15/06/2004 |
There are too many species included in the mandatory fish species list. Are all these species important? What is the economic rationale for the fish species list? We need not worry about Atlantic Sturgeon and dolphins as they can’t survive in the channel anyway.
|
| 291 |
15/06/2004 |
Can the AMEC Study Team predict the future of salmon in the Petitcodiac River in 20 years if the river is restored? Will there be a lucrative commercial fishery if the Petitcodiac River is restored?
|
| 292 |
15/06/2004 |
A modelling workshop, similar to the 2002 workshop, must be held in the future to provide everyone with the PRC EIA modelling results on the options.
|
| 293 |
15/06/2004 |
The AMEC Study Team should visit Cape Enrage and examine the river’s energy.
|
| 294 |
15/06/2004 |
Other independent modellers should review the results before it reaches the government decision makers. Their point of view would be interesting. People all over the world are interested in this EIA.
|
| 295 |
15/06/2004 |
What about sewage from the Moncton plant coming upstream with the tides and contaminating the river?
|
| 296 |
15/06/2004 |
The EIA recommendations must lead to community healing through the dissemination of compete and accurate knowledge.
|
| 297 |
15/06/2004 |
Silt problem is not just tidal, it is also related to local construction practices: silt from Johnathon Creek, Rural Estates, dirt roads in new subdivisions, etc., are clogging the infrastructure. This cannot all be blamed on the causeway.
|
| 298 |
19/07/2004 |
Are the historical photos of the Petiticodiac River included in the Petitcodiac River Causeway EIA presentations taken at high tide or low tide?
|
| 299 |
19/07/2004 |
When were the Moncton landfill sites in operation? |
| 300 |
19/07/2004 |
Does the Full Cost Accounting evaluate the value of the headpond for fire fighting e.g. water bombers and fire trucks access?
|
| 301 |
19/07/2004 |
Are there alternate water sources in the area for fire fighting e.g. Shepody Bay, Bay of Fundy, Shediac Bay?
|
| 302 |
19/07/2004 |
Can water bombers fill up with salt water?
|
| 303 |
19/07/2004 |
There is a difference in Quebec water bombers versus New Brunswick water bombers.
|
| 304 |
19/07/2004 |
Who is the owner of the land in the headpond? Does more than one government department own the land in the headpond?
|
| 305 |
19/07/2004 |
How does the Full Cost Accounting do an analysis if the headpond was eliminated?
|
| 306 |
19/07/2004 |
The headpond has been used by the City of Moncton and Town of Riverview fire trucks for fire fighting during two drought seasons prior to 2004.
|
| 307 |
19/07/2004 |
The Town of Riverview Fire Department currently fills their fire trucks from the headpond during equipment testing and training. Recently the Riverview Fire Department submitted an application to the Environmental Trust Fund for an underground storage tank at the new fire station to be used for testing and training. However, the application was not approved.
|
| 308 |
19/07/2004 |
Can the headpond be used for drinking water if properly treated?
|
| 309 |
19/07/2004 |
Has a report been prepared pre-causeway or post-causeway to determine if the headpond water can be treated and used for drinking water?
|
| 310 |
19/07/2004 |
In June 2004 an Atlantic Sturgeon approximately 7 feet long was observed at the Gunningsville Bridge. However, it later died.
|
| 311 |
19/07/2004 |
Is the AMEC Study Team evaluating the sediment samples taken near the landfill site for contamination? What parameters are being investigated during the EIA soil analysis?
|
| 312 |
19/07/2004 |
Does the sediment deposition directly in front of the Moncton landfill site act as a filter for the landfill site leachate?
|
| 313 |
19/07/2004 |
Has the AMEC Study Team interviewed the Mosquito Control Board?
|
| 314 |
19/07/2004 |
At the 2002 Modelling Workshop, experts from around the world were concerned with the limited data and information on the Petitcodiac River and how well this dynamic river could be modelled. How is the AMEC Study Team addressing these issues?
|
| 315 |
19/07/2004 |
Where will the partial bridge be located and how many meters from the Town of Riverview shoreline?
|
| 316 |
19/07/2004 |
If a partial bridge is installed will the causeway gate infrastructure be in filled with riprap?
|
| 317 |
19/07/2004 |
If a partial bridge is installed or the causeway gates open will the riverbanks be protected with riprap in the areas where property/recreational/tourism development currently exists?
|
| 318 |
19/07/2004 |
Do the individuals that support the causeway removal believe the river will be restored to its original state prior to causeway construction? Do they understand the river will have to be dredged to restore it to pre-causeway condition? Is this dredging cost to be included in the Full Cost Accounting?
|
| 319 |
19/07/2004 |
Will the partial bridge replace the causeway?
|
| 320 |
19/07/2004 |
Has the AMEC Study Team found a viable fish passage facility that will work in the Petitcodiac River?
|
| 321 |
19/07/2004 |
Is the AMEC Study Team looking at innovative approaches to fish passage, instead of using an existing facility? Can we create a new type of fish passage facility that would work in the Petiticodiac River?
|
| 322 |
19/07/2004 |
Are there fish passage facilities/fishways that have been installed in other areas of the world that are working successfully? What is the success rate of fishways in various areas?
|
| 323 |
19/07/2004 |
What about mosquitoes and the West Nile Virus? The last time the causeway gates were opened the mosquito population increased significantly.
|
| 324 |
19/07/2004 |
Please confirm if the AMEC Study Team has reviewed previous reports developed by the Town of Riverview regarding concerns about residential, commercial and recreational development along the headpond and estuary? The Town of Riverview has made significant financial investments along the headpond and river.
|
| 325 |
19/07/2004 |
Is the Status Quo an option?
|
| 326 |
19/07/2004 |
Why is the Status Quo referred to as a baseline condition?
|
| 327 |
22/07/2004 |
How large is the Petitcodiac River Watershed?
|
| 328 |
22/07/2004 |
Local residents in the Petitcodiac River Watershed prior to causeway construction use to fish with a ball of worms on a string when the tidal bore was coming in. Fished for an eel - like species with flesh similar to tomcod.
|
| 329 |
22/07/2004 |
Was the Petitcodiac River Causeway construction successful in preventing flooding of the salt water on the farmland above the Causeway structure?
|
| 330 |
22/07/2004 |
Prior to Causeway construction, many individuals used to walk on the riverbed. In fact, you could tell the tidal bore was coming by feeling the vibration of the riverbed. The bed was not mud rather consolidated material.
|
| 331 |
22/07/2004 |
Is there concern if the gates are open, the landfill site will erode?
|
| 332 |
22/07/2004 |
Is the Petitcodiac River riverbed elevation still rising?
|
| 333 |
22/07/2004 |
Will the lobster and scallop industry in the Bay of Fundy be affected if the gates are open?
|
| 334 |
22/07/2004 |
Will the river be restored to pre-causeway conditions if the gates are open?
|
| 335 |
22/07/2004 |
Has the AMEC Study Team completed detailed fieldwork to confirm the Petitcodiac River bottom and width is changing?
|
| 336 |
22/07/2004 |
Has AMEC Study Team reviewed the volume of fish in the Petitcodiac River pre-causeway, directly after causeway construction and now?
|
| 337 |
22/07/2004 |
Was the AMEC Study Team fieldwork completed at high or low tide?
|
| 338 |
22/07/2004 |
Is there enough fish in the river to invest thousands of dollars to restore fish passage?
|
| 339 |
22/07/2004 |
Does the number of visits on the website increase when there is a press release or letter(s) to the editor?
|
| 340 |
22/07/2004 |
Is the project website an effective communication tool?
|
| 341 |
22/07/2004 |
Who is visiting the website?
|
| 342 |
22/07/2004 |
Is the AMEC Study Team reviewing how the erosion of the riverbed will affect existing and future development along the Petitcodiac River? E.g. infrastructure, tourism, recreation, landfill site, etc.
|
| 343 |
22/07/2004 |
In a couple of years, will the Petitcodiac River directly in front of the City of Moncton become a marsh?
|
| 344 |
22/07/2004 |
Does France, for example or other places in the world have the same type of fish passages?
|
| 345 |
22/07/2004 |
Is the general public and stakeholders both upstream and downstream of the causeway concerned about the sewage treatment plant discharge if the gates are open or a partial bridge is installed?
|
| 346 |
22/07/2004 |
Would the fish recognize the difference between primary and secondary sewage treatment? In fact, secondary treatment will increase ammonia content that is harmful to fish.
|
| 347 |
22/07/2004 |
Is the major concerns outlined in the Petitcodiac River Causeway EIA presentation listed in order of importance?
|
| 348 |
22/07/2004 |
One of the benefits of fresh and saltwater wetlands since the causeway has been built is there is a whole new kind of wildlife present.
|
| 349 |
22/07/2004 |
Does the Petitcodiac River Causeway EIA address the positive effects that have developed since Causeway construction as well as the negative effects?
|
| 350 |
22/07/2004 |
Does the modelling component of the project address the options including the status quo currently and 20 to 30 years in the future?
|
| 351 |
22/07/2004 |
Has the AMEC Study Team considered that the use of farmland may decrease due to urbanism in the future? Is the AMEC Study Team reviewing future trends? We must focus on existing situations and carry these situations forward.
|
| 352 |
22/07/2004 |
If it is determined the current farmland is unproductive, would the dykes along the Petitcodiac River be restored?
|
| 353 |
22/07/2004 |
Where does all the sediment go in the fall and winter?
|
| 354 |
22/07/2004 |
If the causeway gates are open or a bridge is installed and significant erosion occurs along the riverbeds, is there a danger the amount of sediment in the water will increase?
|
| 355 |
22/07/2004 |
Will there be future workshop(s) to discuss the modelling results and socio-economic issues?
|
| 356 |
22/07/2004 |
When will the Draft PRC EIA Report be released to the stakeholders, public and Aboriginal community?
|
| 357 |
22/07/2004 |
When will the Provincial and Federal Governments make a decision?
|
| 358 |
22/07/2004 |
How long it would take for the Lieutenant Governor in Council to make a decision?
|
| 359 |
22/07/2004 |
When would the selected option be implemented?
|
| 360 |
22/07/2004 |
What could be done to the Petitcodiac River to return the river to its original state or pre-causeway conditions?
|
| 361 |
22/07/2004 |
If a bridge was constructed versus opening the causeway gates would the river be restored?
|
| 362 |
22/07/2004 |
Will ships be able to sail up the Petitcodiac River once it is restored?
|
| 363 |
22/07/2004 |
Can the proposed 275 m wide bridge size be increased to maximize on restoring the river width? Why is the AMEC Study Team only investigating one bridge size?
|
| 364 |
22/07/2004 |
Is it possible to take the top four feet off the saltwater marshland vegetation growth to accelerate erosion of the riverbanks and restore the Petitcodiac River to its original state or pre-causeway conditions?
|
| 365 |
22/07/2004 |
Will the EIA report outline the schedule for constructing a bridge or opening the gates at different periods or seasons or opening all 5 gates all the time?
|
| 366 |
22/07/2004 |
Will the AMEC Study Team be addressing the positive features of the river restoration in addition to selling the river as a transportation route for the resident fish?
|
| 367 |
06/11/2004 |
The Petitcodiac Riverkeeper recommended the AMEC Study Team review two previous EIA reports completed in 1996 and 1998 when the Petitcodiac River Causeway gates were opened. The Niles report concluded that fish passage was problematic and that a solution was required. There was a legal obligation to find that solution. Therefore, in accordance with the Fisheries Act, Niles recommended an EIA study be completed to find a solution to fish passage in the Petitcodiac River. |
| 368 |
06/11/2004 |
Please review and explain the operation of the current causeway gates and the 2004-2005 gate management plan. |
| 369 |
06/11/2004 |
Does the AMEC Study Team have all 100 studies that have been completed on the Petitcodiac River? Are the studies incorporated into one file or several files? |
| 370 |
06/11/2004 |
Has the AMEC Study Team verified the role fish played in the offshore fishery and the recruitment of stock? |
| 371 |
06/11/2004 |
How long was the fieldwork carried out by the AMEC Study Team? Where were the depth of disturbance gauges installed and the time frame they were monitored?
|
| 372 |
06/11/2004 |
Did the AMEC Study Team complete a digital elevation model and develop a model for the estuary? What resolution is the computer modelling?
|
| 373 |
06/11/2004 |
Are all four options still being carried forward in the Petitcodiac River Causeway Environmental Impact Assessment?
|
| 374 |
06/11/2004 |
Where did the AMEC Study Team obtain information on the Atlantic Sturgeon in the Petitcodiac River migrating to Salisbury prior to 1966? Are there pre-causeway reports confirming the sturgeon migrated to Salibury? |
| 375 |
06/11/2004 |
Please explain why striped bass are not listed on the fish species list that require passage at the Petitcodiac River Causeway.
|
| 376 |
06/11/2004 |
Did the fish population in the Petitcodiac River decline significantly after the causeway construction? |
| 377 |
06/11/2004 |
How does the vertical slot fishway work? |
| 378 |
06/11/2004 |
Did the AMEC Study Team test fish toxicity? Are the fish in the Petitcodiac River estuary healthy? Is the AMEC Study Team looking comprehensively at recreation along the entire estuary as well as the headpond? Is the AMEC Study Team going to discuss flooding in relation to the Status Quo? What will happen to the Petitcodiac River if we maintain the Status Quo? In the months of July and August is the water quality below regulation requirement for recreation? Is the reduction in the dissolved oxygen level in the Petitcodiac River estuary a result of the Greater Moncton sewage treatment plant effluent? Is there a health and safety issue in relation to recreational boating in the estuary? Is it safe to kayak in the Petitcodiac River? |
| 379 |
06/11/2004 |
Is there shoreline erosion downstream? Is the amount of erosion reduced with the reduced water volume? Did the AMEC Study Team locate any archeological and heritage sites along the Petitcodiac River or in the watershed? Is there data available regarding historical shoreline erosion? |
| 380 |
06/11/2004 |
Given the presence of an important Ramsar site, is the infilling below Hopewell Cape going to stop? Where is the infilling downstream of the causeway going to stop? |
| 381 |
06/11/2004 |
Can we predict the river change beyond Cape Enrage? If the causeway piers are removed as described in Option 3 will the causeway structure have to be reinforced? |
| 382 |
06/11/2004 |
Please explain why Option 2 will not be fully assessed in the EIA report? Will Options 3 and 4 eliminate the headpond? Will headpond fill in with sediment and salt water? |
| 383 |
06/11/2004 |
It is my understanding the fishway will be eliminated in this EIA Study? Is this correct? If we can put people on the moon, why can't we find a solution to this fish passage? Is the headpond going to be drained? When will the public and stakeholders have access to the dissolved oxygen level readings in the headpond? Is the AMEC Study Team recommending the headpond will be deleted? How is the fish going to get past Sal;isbury if you don't have enough water now to go through the fishway? Why has the AMEC Study Team not released any information describing the conditions in the headpond including dissolved oxygen levels, and released biophysical and socio-economic component study reports? Why is this information not available at this workshop? |
| 384 |
06/11/2004 |
Where is Outhouse point located? Will sediment infilling continue if the gates are open or partial bridge is installed? Where does the water go if the river continues to fill with silt? In the future will the Petitcodiac River return to the pre-causeway conditions if Option 3 or Option 4 is completed? What location along the Petitcodiac River has the most severe inflling or siltation? |
| 385 |
06/11/2004 |
The AMEC Study Team states there is not enough fresh water in the Petitcodiac River estuary? Has the team considered the amount of water going to the Turtle Creek Reservoir? How will the causeway traffic circle flooding improve with Option 3 and Option 4? If the causeway was not constructed would the Petitcodiac River still be infilling due to the high total suspended solids in the river? This EIA study only deals with fish passage? The AMEC Study Team's only cares about fish passage up the Petitcodiac River not the cost or the risks of opening the causeway.
|
| 386 |
06/11/2004 |
Why did the AMEC Study Team not model the river up to 40 years in the future versus 20 years? Does the workshop presentation today include a slide that indicates 40 year prediction? Will the Petitcodiac River return to 1966 conditions? |
| 387 |
06/11/2004 |
Will there be any additional erosion in the Petitcodiac River after 20 years if the causeway gates are open or a partial bridge is installed? |
| 388 |
06/11/2004 |
Why are the tidal prisms upstream of the causeway not the same as 1966? |
| 389 |
06/11/2004 |
Has the AMEC Study Team considered global warming and rising sea levels? |
| 390 |
06/11/2004 |
If Option 3 modified is carried out will the high water velocity at the causeway affect fish passage? Is there any restriction if the causeway gates are open? Do fish move on a rising tide? Is there a concern about gate sills interferring with fish passage? Is Option 3 (modified) viable? Why is the erosion of the river banks different from 5 to 20 years? Will there be erosion at the landfill sites? Will there be any changes at the Gunningsville Bridge cross section if a partial bridge is installed? Will there be any effect on the lobster and scallop fishery in Shepody Bay? How much silt will be deposited at the causeway? Will the dilution factor in the river improve under the Status Quo condition? What is the impact on shorebirds and flooding if the Status Quo remains? |
| 391 |
06/11/2004 |
Will there not be a net transport of sediment upriver if the gates are opened, like there was in 1989 during the trial gate openings? |
| 392 |
06/11/2004 |
The AMEC Study Team is to be commended on what they have done and now know. The public consultation for this EIA Study has been excellent. I worked with Eugene Niles and I think he would be pleased. The previous 120 studies were not real studies; about 15-20 only were real studies. Certainly an EIA study was needed for this project and it was the right approach. This is a very thorough EIA Study and well done by the team. The Alma Fishermen are concerned with the how fast the sediment will move downstream and its impact on the lobster and scallop fishing industry. What is the status on the full cost accounting? How much has GPI Atlantic been involved in the project to date? Are there any more public consultation events in the future? |
| 393 |
06/11/2004 |
Please confirm the modelling assumptions regarding sediment dynamics including flocculation and fluid mud? How confident is the AMEC Study Team in the modelling results with regards to erosion and deposition? What is the error bar for the modelling? Does the EIA study address sedimentation in the Bay of Fundy? |
| 394 |
06/11/2004 |
Opening the causeway gates will cause the headpond to fill with silt. How will Option 3 (modified) and Option 4 resolve the silt build-up? In 1988 there was a million tonnes of silt deposited in the headpond when the causeway gates were opened. Will the same siltuation occur today if the gates are opened? In the 1800's Halls Creek infilled with silt so why will it not infill today if the gates are opened? |
| 395 |
06/11/2004 |
What will happen with the tidal bore if the causeway gates or partial bridge is installed? Will the modelling predict extreme events like the Saxby Gale? |
| 396 |
06/11/2004 |
How much will the tidal bore increase if Option 3 (modified) or Option 4 is carried out? What will happen if Option 4, a partial bridge, is selected and the causeway gates are opened immediately? Will the opening of the causeway gates affect the construction of the partial bridge? Is the erosion worse on the Riverview side if the causeway gates are opened or a partial bridge is installed? Is the landfill site at risk when the causeway gates are opened or partial bridge installed? |
| 397 |
06/11/2004 |
It is my understanding the EIA objective is to improve fish passage. Is a partial bridge a faster progression to restore the Petitcodiac River? Is the rate of river recovery a requirement of the EIA Study? |
| 398 |
06/11/2004 |
I understand the study mandate, but I represent people not fish. If the causeway gates are opened or a partial bridge installed will the Petitcodiac River widen at Hopewell Cape? How wide is the river in the headpond? |
| 399 |
06/11/2004 |
How far above the causeway will the head of the tide be if the causeway gates are opened or a partial bridge is installed? How will opening the causeway gates or installing a partial bridge improve the water quality when there is good quality fresh water in the headpond now? What is the cost to remedy/improve the current water quality downstream of the causeway? Will the lobster fishery be affected if the causeway gates are opened or a partial bridge installed? Will the headpond disappear quickly? |
| 400 |
06/11/2004 |
The AMEC Study Team are to be commended for a very thorough EIA Study. The Team's expertise is very impressive. Will there be a decline in the property value in the headpond if the gates are open of a partial bridge is installed? |
| 401 |
06/11/2004 |
Why is this EIA study all about fish? What is the impact on Hillsborough? The Alma lobster fishermen are very concerned about the silt moving downstream if the causeway gates are opened or if a partial bridge is installed. What will happen to the wetlands, water quality, etc? Where will the funding come from for this project? |
| 402 |
06/11/2004 |
The AMEC Study Team are to be commended for the factual information presented at this workshop. When will the EIA report and fieldwork data be available to the public? When is the next public session? |
| 403 |
06/11/2004 |
Will the EIA report outline cost sharing methods between provincial and federal governments and municipalities? |
| 404 |
06/11/2004 |
Is the EIA Study on schedule? |
| 405 |
06/01/2005 |
What is the total cost of the EIA study from day one? |
| 406 |
06/01/2005 |
Has the Study Team investigated the commercial fishery in the Bay of Fundy? |
| 407 |
06/01/2005 |
Good presentation and abundance of technology used on this project. Inquired if the two levels of government (provincial and federal) will come to a decision at the end of the PRC EIA when the final EIA report is complete. The decision to construct the causeway was a rush decision. Is there light at the end of the tunnel for the Petitcodiac River? |
| 408 |
06/01/2005 |
It appears the rationale of the original terms of reference was to restore fish passage. Why open the causeway gates or install a partial bridge, when the cost could exceed 15 to 20 million dollars? The decision is open the gates will not be popular with the residents living on the headpond. Is it worth spending millions of dollars to restore fish passage? Is it worth spending the money when new species have been added in the headpond? What was the justification for the overall EIA objective? |
| 409 |
06/01/2005 |
What would be the economic impact on the fishery in the Petitcodiac River estuary and the Bay of Fundy if the causeway gates were opened or a partial bridge was installed? |
| 410 |
06/01/2005 |
Would rainbow trout and salmon spawn in the headpond? |
| 411 |
06/01/2005 |
Has the Study Team contacted the Nova Scotia fishermen to confirm if the Petitcodiac River Causeway has impacted on their fishery e.g. salmon? Is the Study Team addressing the farmland which will have to be dyked if the causeway gates are open or a partial bridge is installed? Is the Study Team reviewing the loss of the headpond and impact to the ecosystems that have been developed during the past 30 years? Did the Russians fish in the Bay of Fundy and deplete the fish stock? Where did the sediment built up come from? |
| 412 |
06/01/2005 |
With the fish depletion in the ocean and the Bay of Fundy, would we be able to justify for all the cost of the EIA study and the fishway? It is my understanding the fish are not traveling up the Petitcodiac River and the lobster fishery is doing well. |
| 413 |
06/01/2005 |
Beautiful presentation this morning! Please explain why there was not a word on the new bridge. Would the bridge piers and adjacent channel be eroded if the causeway gates are open or a partial bridge is installed? |
| 414 |
15/03/2005 |
I take it that the status quo is not acceptable from any perspective? |
| 415 |
15/03/2005 |
How will the course of the river change (under Options 3 and 4)? |
| 416 |
15/03/2005 |
What about the potential for erosion in the vicinity of the landfill and in Riverview where the Home Hardware and Fire Station was constructed on fill material? |
| 417 |
15/03/2005 |
Any evidence of water quality degradation from the landfill? |
| 418 |
15/03/2005 |
Will the modelling predict the amount or percentage of sediment that will move downstream if the causeway gates are opened or a partial bridge installed? |
| 419 |
15/03/2005 |
You mentioned that a step-wise approach was taken with the hydraulic and sediment modeling whereby you progressively looked at zero, one and two dimensional modelling. Was the modeling limited to numerical models or were physical models constructed as well? Also, is there any statistical confidence levels associated with the model predictions? |
| 420 |
15/03/2005 |
Was the farmland dyked prior to causeway construction? The existing dykes have not been maintained by the government departments or farmers for a number of years. |
| 421 |
15/03/2005 |
Do you think that environmental impacts from the former Moncton landfill will become a problem with a more open channel? |
| 422 |
15/03/2005 |
“Where did the water go” since the construction of the causeway? |
| 423 |
15/03/2005 |
Some downstream lobster fishing activity has reportedly moved closer to shore. How will this fishery be affected by the additional eroded material if the river is returned to a more natural flow? |
| 424 |
15/03/2005 |
Has anyone looked into the possibility of suing the government over building the causeway? |
| 425 |
15/03/2005 |
Why was the study (primarily) limited to fish passage and not restoration of the river? |
| 426 |
15/03/2005 |
Is the EIA study done? |
| 427 |
15/03/2005 |
When they decided to build the causeway in 1968, did the designers know all the impacts it would have on fish passage and the Petitcodiac River? |
| 428 |
15/03/2005 |
What are the next steps? |
| 429 |
15/03/2005 |
With Options 3 or 4, the Petitcodiac Lake or headpond will disappear? |
| 430 |
15/03/2005 |
What timeframe or urgency do we have for the fish population if we do not proceed with modifications to the Petitcodiac River Causeway? |
| 431 |
15/03/2005 |
What was the rational behind the construction of the causeway? |
| 432 |
15/03/2005 |
What is going to happen with the silt/sediment in the river if there are modifications completed to the causeway? |
| 433 |
15/03/2005 |
Is there a spillway in the causeway? |
| 434 |
15/03/2005 |
Is there a possibility that only 2 gates will be opened initially to confirm if the modelling predictions are correct? |
| 435 |
15/03/2005 |
If we proceed with construction of a partial bridge what quantity of dredging is required? Will there be information included in the EIA report outlining the dredge material amount, cost and where it will be disposed of? |
| 436 |
15/03/2005 |
Is there any damage or erosion expected to Outhouse Point if a partial bridge is installed? |
| 437 |
15/03/2005 |
Will the landfill site be protected? |
| 438 |
04/04/2005 |
Has the AMEC Study Team investigated opening the causeway gates as soon as the ice breaks? |
| 439 |
04/04/2005 |
Opening the causeway gates and removing three concrete piers would not restore the Petitcodiac River to its natural state as the causeway opening width creates a bottleneck in the river. |
| 440 |
04/04/2005 |
Would one of the underlying structures to be done for this EIA address maintaining the headpond? |
| 441 |
04/04/2005 |
Property owners located on the headpond would not accept loss of the headpond or the body of water located in front of their homes. However, the best option is Option 4C which installs a bridge in the center of the Petitcodiac River channel but limited government funding may affect this preferred option. |
| 442 |
04/04/2005 |
Would the salt water wedge continue up to Salisbury if the causeway gates were opened or a partial bridge is installed? |
| 443 |
04/04/2005 |
What was the accuracy of the computer modelling that was completed on this EIA Study? |
| 444 |
04/04/2005 |
The modelling results appear to indicate that the Petitcodiac River will continue to silt in and if the Status Quo remains for the next 20 years, a bridge will not be required as you will be able to walk from the City of Moncton to the Town of Riverview. |
| 445 |
04/04/2005 |
Have the designers taken into account the river widening during the planning stage of the new Petitcodiac River bridge if the government was to proceed with Option 3 or Option 4? |
| 446 |
04/04/2005 |
FFFN do not harvest from the headpond mudflats due to Agricultural run off which stems from the Anagance and North rivers, both of which are tributaries to the Petitcodiac River. FFFN do not harvest in areas where known contamination from Agricultural runoff occurs as it also contaminates the species being harvests (whether it is a plant, fish or animal species). Once the gates are taken out and tidal action of the river is allowed to return it will in turn flush this contamination to levels acceptable to return harvesting species in this area. |
| 447 |
04/04/2005 |
Would the EIA Study address the adverse environmental effects the causeway has on the entire Petitcodiac River watershed including fish migration and other ecosystems? |
| 448 |
04/04/2005 |
Would the modelling address the dwarf wedge mussels return to the Petitcodiac River? |
| 449 |
04/04/2005 |
Would the tidal bore be returned if the causeway gates were opened or if a partial bridge was installed? |
| 450 |
04/04/2005 |
FFFN confirmed Option 4C is their preferred option as it will help in the eventual restoration of the Petitcodiac River, to its natural state. |
| 451 |
04/04/2005 |
Did the AMEC Study Team investigate dam removals in the State of Maine including lessons learned from those dam removals? |
| 452 |
04/04/2005 |
During the last opening of one of the Memramcook causeway gates, the increased water velocity caused severe bank erosion. A similar environmental effect would likely occur along the Riverview side of the Petitcodiac River if the causeway gates were open. |
| 453 |
17/05/2005 |
Will the Petitcodiac River be restored to its original state in width and depth if a partial bridge is installed or all the causeway gates are opened? |
| 454 |
17/05/2005 |
How long will it take to notice a change in the river width and depth if a partial bridge is installed or if all the causeway gates are opened? |
| 455 |
17/05/2005 |
During the field investigations, were any of the fish found to have poor health conditions in the headpond or the estuary? |
| 456 |
17/05/2005 |
Why wasn't there an environmental impact assessment completed prior to the construction of the causeway? |
| 457 |
17/05/2005 |
How much will it cost to construct a partial bridge? |
| 458 |
17/05/2005 |
Who will fund the cost of construction of the selected option and mitigative measures? |
| 459 |
17/05/2005 |
Will the project funding be provided by the taxpayers and will taxes increase? |
| 460 |
17/05/2005 |
When will government make a decision on which option will be carried out? |
| 461 |
10/22/2005 |
What was the federal financial contribution towards the construction of the causeway? |
| 462 |
10/22/2005 |
With respect to the fish species requiring migration at the causeway, what were they prior to the construction of the causeway, and what are they now?
|
| 463 |
10/22/2005 |
Have you identified the locations along the river bank where the Moncton infrastructure such as storm sewage and storm water runoff enter the river?
|
| 464 |
10/22/2005 |
You have indicated that the lobster fisheries will not be affected by opening the causeway, has there been any studies conducted to verify that?
|
| 465 |
10/22/2005 |
What is the bacteria count downstream of the causeway under the present conditions?
|
| 466 |
10/22/2005 |
Could the concentrations of hydrocarbons and metals be related to the leachate from the Moncton landfill?
|
| 467 |
10/22/2005 |
Have you identified the potential sources of hydrocarbons and metals observed in the Petitcodiac River?
|
| 468 |
10/22/2005 |
Do all the Project Options which have different costs associated with them meet the biological requirements for fish passage?
|
| 469 |
10/22/2005 |
What is the difference in benefits between Options 4A and 4B?
|
| 470 |
10/22/2005 |
What is the time frame when the Petitcodiac River will reach its natural state after the removal of the causeway?
|
| 471 |
10/22/2005 |
What is the quantity and the quality of the surface water coming into the Petitcodiac River?
|
| 472 |
10/22/2005 |
Will monitoring of water quantity and quality be continued over the long-term by a certain level of government?
|
| 473 |
10/22/2005 |
What are the basic differences between Option 3 and Options 4A, 4B and 4C in the downstream reaches of the Petitcodiac River?
|
| 474 |
10/22/2005 |
Where exactly would the riprap, for erosion protection, be installed at the Château Moncton?
|
| 475 |
10/22/2005 |
Considering that the landfill cover material is fairly impermeable, why do we need erosion protection measures for contingency now and not five or ten years in the future?
|
| 476 |
10/22/2005 |
Can we accelerate the gate opening process, in a safe way, during the implementation of a Project Option?
|
| 477 |
10/22/2005 |
Where was the location of the main channel at the causeway location prior to the construction of the causeway?
|
| 478 |
10/22/2005 |
If we do not know the exact sources of hydrocarbons and metals, how do we know that the Project Options will improve water quality?
|
| 479 |
10/22/2005 |
What do we have today for fish count and what are the projected fish counts for the nine species under the various Project Options?
|
| 480 |
10/22/2005 |
Will all of the Project Options address the low oxygen levels observed within certain reaches of the river?
|
| 481 |
10/22/2005 |
Have you looked at phosphorous levels in the river system?
|
| 482 |
10/22/2005 |
Under the Project Options, will there be enough water to wash out the contaminants such as phosphorous and others in the waters of the Petitcodiac River?
|
| 483 |
10/22/2005 |
Have you done any studies on the River Hebert and the Salmon River to determine the reasons for the reduction in their fish population?
|
| 484 |
10/22/2005 |
How are you going to ensure the river will not be contaminated by leachate from the landfill under Option 3?
|
| 485 |
10/22/2005 |
What guarantees are there that fishermen would get compensated every year for their losses? Who will guarantee these compensations?
|
| 486 |
10/22/2005 |
What about losses in the agriculture sector? Will compensations be provided?
|
| 487 |
10/22/2005 |
If you are providing access areas for mosquito growth, how are you going to address the increase in mosquito population?
|
| 488 |
10/22/2005 |
Is the present infilling within the headpond coming from upstream sources and soil erosion or is it coming through the fishway with tidal water?
|
| 489 |
10/22/2005 |
The tidal bore is going to improve under all options, have you identified the difference in tidal bore improvement under all options? Will the tidal bore improvement be the greatest under Options 4B and 4C?
|
| 490 |
10/22/2005 |
Under the Project Options, will the deposition of tidal sediment in the headpond result in the reduction of the tidal prism?
|
| 491 |
10/22/2005 |
Have you studied the history of flooding in the Moncton/Riverview area over the past 100 years?
|
| 492 |
10/22/2005 |
The costs associated with doing nothing at the causeway should be clearly identified and compared with the benefits associated with the Project Options.
|
| 493 |
10/22/2005 |
Have you talked to developers in the area during your assessment of the impacts on property value?
|
| 494 |
10/22/2005 |
Can we stop the silt building up in the rivers of the upper Bay of Fundy?
|
| 495 |
10/22/2005 |
Where would the sediment end up in the lower reaches of the Petitcodiac River? Will it be depositing in the outer Bay of Fundy?
|
| 496 |
10/22/2005 |
Are there ways to increase freshwater flow within the Petitcodiac River by removing barriers further upstream?
|
| 497 |
10/22/2005 |
With the present technology and engineering knowledge, can we r |