![]() |
||||||||||||||||||||||||||||||||||||||||
| Français | ||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||
TABLE OF CONTENTS1.0 INTRODUCTION
2.0 PRELIMINARY DRAFT TERMS OF REFERENCE FOR SOCIO-ECONOMIC COMPONENT STUDIES2.1 LAND USE AND VALUE 2.1.1 Background 2.1.2 Issues and Concerns 2.1.3 Project Environmental Effects 2.1.4 Cumulative Environmental Effects 2.1.5 Mitigation Options 2.1.6 Information Requirements2.2 LABOUR AND ECONOMY 2.2.1 Background 2.2.2 Issues and Concerns 2.2.3 Project Environmental Effects 2.2.4 Cumulative Environmental Effects 2.2.5 Mitigation Options 2.2.6 Information Requirements2.3 MUNICIPAL SERVICES AND INFRASTRUCTURE 2.3.1 Background 2.3.2 Issues and Concerns 2.3.3 Project Environmental Effects 2.3.4 Cumulative Environmental Effects 2.3.5 Mitigation Options 2.3.6 Information Requirements2.4 TRANSPORTATION NETWORK 2.4.1 Background 2.4.2 Issues and Concerns 2.4.3 Project Environmental Effects 2.4.4 Cumulative Environmental Effects 2.4.5 Mitigation Options 2.4.6 Information Requirements2.5 VESSEL TRAFFIC AND NAVIGATION 2.5.1 Background 2.5.2 Issues and Concerns 2.5.3 Project Environmental Effects 2.5.4 Cumulative Environmental Effects 2.5.5 Mitigation Options 2.5.6 Information Requirements2.6 ARCHAEOLOGY AND HERITAGE RESOURCES 2.6.1 Background 2.6.2 Issues and Concerns 2.6.3 Project Environmental Effects 2.6.4 Cumulative Environmental Effects 2.6.5 Mitigation Options 2.6.6 Information Requirements2.7 TOURISM 2.7.1 Background 2.7.2 Key Issues and Concerns 2.7.3 Project Environmental Effects 2.7.4 Cumulative Environmental Effects 2.7.5 Mitigation Options 2.7.6 Information Requirements2.8 RECREATION 2.8.1 Background 2.8.2 Key Issues and Concerns 2.8.3 Project Environmental Effects 2.8.4 Cumulative Environmental Effects 2.8.5 Mitigation Options 2.8.6 Information Requirements2.9 PUBLIC HEALTH AND SAFETY 2.9.1 Background 2.9.2 Issues and Concerns 2.9.3 Project Environmental Effects 2.9.4 Cumulative Environmental Effects 2.9.5 Mitigation Options 2.9.6 Information Requirements |
||||||||||||||||||||||||||||||||||||||||
LIST OF TABLES |
||||||||||||||||||||||||||||||||||||||||
LIST OF ACRONYMS
|
||||||||||||||||||||||||||||||||||||||||
|
This document provides the Terms of Reference (TOR) for the socio-economic component studies of the Petitcodiac River Causeway Environmental Impact Assessment (“EIA”). Comments from the New Brunswick Department of Supply and Services (DSS), the Technical Review Committee (TRC) and participants of the Socio-economic Workshop1 held May 31, 2003, on a preliminary draft of this document have been incorporated into this document. The document describes the elements of the proposed work plan and study for each aspect of the socio-economic environment that may be affected by the Project Options or Status Quo. The socio-economic component of the Petitcodiac River Causeway Environmental Impact Assessment is comprised of the following sub-components:
The socio-economic component study TOR reflects the outcome of the work undertaken in the Phase 1 - Scoping of the EIA, as outlined in Section 2.1.1 of the Terms of Reference for the Environmental Impact Assessment for the Modifications to the Petitcodiac River Causeway, AMEC Earth & Environmental Limited (AMEC), 2003. These scoping activities have included discussions regarding the confirmation of project objectives, preliminary hydrodynamic and sediment transport modelling and the evaluation of existing information and identification of data gaps. In recommending the work plan, linkages to the Hydrodynamic and Sediment Transport Modelling and Biophysical Component studies are made, so that related issues can be addressed in the TOR for those studies. It is important to recognise that these studies are intended at providing the information and analyses necessary to conduct the EIA. The Socio-Economic Component Study will not include environmental effects predictions or analyses, as these will be done in Phase 3 of the EIA. A summary of the items discussed at the Socio-economic Workshop regarding each socio-economic sub-component have been reported in the document: Summary of the Socio-Economic Workshop, June, 2003. In recommending the work plan, linkages to other studies (Hydrodynamic and Sediment Transport Modelling, Socio-Economic Component Studies and Biophysical Component Studies) are made, so that linking issues can be addressed later in the development of the TOR for those studies. It is important to recognize that these studies are intended at providing the information and analyses necessary to conduct the EIA. The Biophysical Component Study will not include environmental effects predictions or analyses, as these will be done in Phase 3 of the EIA. |
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||
|
2.1.1 Background The focus of this portion of the Socio-Economic Component Study is the private and public land that is located within the potential zone of influence of the Project Options and Status Quo. As far back as the time of early European settlement in the area, the Petitcodiac River has had a major influence on the pattern of development. As the principal mode of transportation for several centuries, many of the farms, sawmills, and other sources of employment were located in close proximity to the River. In order to be close to these sources of employment, latter inhabitants clustered in settlements that were oriented to the River. In more recent history, it is largely the aesthetic appeal of the Petitcodiac River that has attracted suburban dwellers and affected development patterns. |
||||||||||||||||||||||||||||||||||||||||
|
Land Use and Property Value Changes Changes to Agricultural Land |
||||||||||||||||||||||||||||||||||||||||
|
It is anticipated that the Project Options could have an environmental effect on the value of the properties in close proximity to the River. To identify the anticipated environmental effects of the Project Options on the private and public land located within the Study Area, a review of the hydrodynamic and sediment transport modelling will be undertaken with special attention to any predicted changes in water levels, erosion, siltation, and physical appearance. The review of modelled changes associated with each Project Option will be augmented by on-site visits to any area of special concern. These changes will be included in an analysis of how they might affect the ability of land users to continue to use their land for current and planned purposes, and to determine if any changes in aesthetics or use could affect the value of property. In order to quantify changes in residential and commercial property value from any environmental effects attributed to the Project Options, sales data will be reviewed to identify “pairs” of sales located within the Study Area. These paired sales, which ideally include both vacant and improved property, will be highly similar except that one sale property would be located on the Petitcodiac River, while the other would not. Any differential would amount to the total monetary enhancement that accrues to a waterfront property located on the Petitcodiac River. This differential will then be applied to affected waterfront property in an effort to gauge the change in value that could occur as a result of the Project Options. Agricultural land will be similarly evaluated by comparing the unit costs of current land sales with upland agricultural land sales, and similar lands sales in Nova Scotia marshlands. |
||||||||||||||||||||||||||||||||||||||||
|
Past and present projects that may have overlapping effects on land use and property value are many and varied. To a large extent, current land use and zoning by-laws act cumulatively on the current land uses and property value. Cumulative environmental effects of the Project Options in combination with these will be considered by establishing the Status Quo, which in this instance is a reflection of the past and present cumulative environmental effects. Future projects, such as the new Petitcodiac River Bridge, may affect land use and value. This and other future projects that will be carried out will be considered in these analyses. Future land development plans already in place may be affected, and as a result changed or denied. |
||||||||||||||||||||||||||||||||||||||||
|
In regard to the private and public land that is located within the Study Area, mitigation could result in a significant reduce the effects on the value of properties located in close proximity to the River. Mitigation can be facilitated by the on-going inclusion of special interest groups and the media in the consultation process, especially as it concerns the selection of the preferred Project Option. The cataloguing and monitoring of the most sensitive properties within the Study Area could be undertaken once the actual work begins. The use of erosion control devices in sensitive areas could mitigate some of the environmental effects. Community enhancement initiatives (e.g., trails, access points, community projects) could also offset some potential land use and/or property value related environmental effects. The agricultural infrastructure upgrade requirements to sustain farmlands will be examined in conjunction with the Municipal Services and Infrastructure sub-component study, as a land use and value mitigation initiative. |
||||||||||||||||||||||||||||||||||||||||
|
Environmental Effects of the Project Options
Data Sources
|
||||||||||||||||||||||||||||||||||||||||
|
2.2.1 Background Each of the four Petitcodiac River Causeway Project Options will generate labour employment and expenditure environmental effects on the local and Provincial economies during the construction phase, as well from ensuing operations and maintenance activities. The Causeway modifications associated with each option will involve varying degrees of economic activity. In addition, employment and economic activity creation or losses may occur in other sectors of the economy, such as tourism or commercial fishing, as a result of the environmental effects of the Project Options. These economic changes will indirectly affect other sectors of the local and Provincial economy through the “spin-offs” of jobs and economic activity generated or loss. |
||||||||||||||||||||||||||||||||||||||||
|
Effects on Jobs and the Economy Local and provincial economies may also be affected positively or negatively by changes to the physical and socio-economic environment attributed to the selected Project Option. For example, modifications to the Causeway and the changes in flow patterns of the River may provide new economic and employment opportunities in tourism, and/or it may result in losses of recreational activities. Gains and losses in employment and economic activity will be derived not only from the direct effects, but also from the indirect “spin-offs” of jobs and employment income generated in other economic sectors. |
||||||||||||||||||||||||||||||||||||||||
|
Existing levels of employment and economic activity in the local Study area will be affected by:
The positive economic effects of the construction activity generated by the implementation of a Project Option will benefit local area residents, provincial labour unions, the construction industry, the business community, and the provincial economy. The direct and indirect (“spin-off) benefits from employment and income generation will be estimated for the construction and operations phases of the Project Options. The changes in flow patterns of the River associated with each of the Project Options will effect economic sectors in different ways, some positively and some negatively. Existing businesses and economic activities that are focused on the current configuration of the River or head pond may be affected negatively by the Project Options. Other existing and new businesses and economic opportunities may be enhanced by the changes attributed to the Project Options. The nature and extent of economic effects will be estimated over the operational period of the Project Options. The direct employment and economic expenditure activities generated or lost in economic sectors affected by the Causeway Project Options will be determined in conjunction with the other socio-economic component studies. The indirect “spin-off” employment and expenditure effects of the changes per Project Option will be estimated for each affected economic sector using Statistics Canada Inverse Matrix Multipliers. This approach will not include a detailed labour market analysis, community development environmental effects assessment, or a special run of project-specific employment and expenditures using the Statistics Canada input-output model. |
||||||||||||||||||||||||||||||||||||||||
The cumulative socio-economic environmental effects of the Project Options are inherently addressed through consideration of the current economies and labour markets. Current baseline conditions are a reflection of past and present projects. Future projects that will be carried out will be captured in the direct and indirect economic sector effects analysis. |
||||||||||||||||||||||||||||||||||||||||
Because construction labour and income creation is considered a positive aspect of any of the Project Options, there will be no need to undertake mitigation. Instead, measures intended to enhance the use of local labour, materials and production inputs of each Project Option will be outlined for the construction and operations phases. Similarly, measures will be pursued to enhance any new developments and/or increased economic activities in sectors affected positively by Project Options. Where losses in economic sectors affected adversely are indicated from the other socio-economic component studies, mitigation measures will be considered. |
||||||||||||||||||||||||||||||||||||||||
2.2.6 Information Requirements Environmental Effects of the Causeway and Project Options Data Sources The potential direct job and expenditure activity gains and losses associated with the other components of the environment will be acquired through consultations with the other Socio-economic and Bio-physical Component Study Team members. |
||||||||||||||||||||||||||||||||||||||||
|
2.3.1 Background The environmental effects on municipal services and infrastructure for each of the Project Options is addressed in this sub-component. The environmental effects on the road system are dealt with in the Transportation Network sub-component of the environment. There are numerous infrastructure components along the Petitcodiac River. The infrastructure components currently serve residents of the municipalities and local service districts located along the banks of the Petitcodiac River. The types of infrastructure include:
1Note that Municipal Services and Infrastructure includes all private and public infrastructure, and underground water and wastewater services. |
||||||||||||||||||||||||||||||||||||||||
Continued Functionality and Effectiveness of Municipal Services and Infrastructure The key issues or concerns associated with municipal services relates primarily to any temporary interference that the Project Options that may have on the water and wastewater services operation and the ability of emergency services (e.g., fire, police, ambulance) during their construction and operation. Further, any Project Option induced demand on municipal services (e.g., due to increases in river related human activity) would be of concern. |
||||||||||||||||||||||||||||||||||||||||
|
The anticipated socio-economic environmental effects of the Project Options and the Status Quo can be divided into two distinct sections as follows:
In conjunction with the hydrodynamic and sediment transport modelling, the areas of the River subject to erosion and sedimentation will be identified. The environmental effects on Infrastructure caused by each Project Option with regards to erosion and/or sedimentation, will then be identified and analyzed. For example, for each Project Option, the costs for maintenance of ditches and outfall structures would be analyzed and compared to the Status Quo. The possibility of having to provide structures protection for the existing Causeway structure, the new Petitcodiac Bridge being constructed at Gunningsville, and the structures constructed in the Project Options resulting from any change in flow, siltation and/or erosion will also be evaluated. As the description of the Project Options is developed and the environmental effects of these are determined, especially related to the flow of traffic, the effects of the Project Options on emergency services will be evaluated. Also, where future changes in land use and businesses related to the Project Options are identified, environmental effects on municipal services will be evaluated. |
||||||||||||||||||||||||||||||||||||||||
|
The description of existing municipal services and infrastructure will establish the cumulative environmental effects of past and present projects that have overlapping environmental effects with those of the Project Options. Future projects that may have overlapping effects on municipal services and infrastructure will also be identified. |
||||||||||||||||||||||||||||||||||||||||
|
For each Project Option and the Status Quo, the environmental effects on Infrastructure may be reduced with the use of mitigation measures. Potential mitigation measures are:
Mitigation of municipal services may include measures to limit or avoid underground services disruptions, and planning for emergency services that are adversely affected by the construction or operation of the Project Options. |
||||||||||||||||||||||||||||||||||||||||
Environmental effects of the Project Options All existing information available from the municipalities, provincial and or federal government agencies, crown corporations, and all other public and private sources, will be acquired to assess the environmental effects on all known existing infrastructure. All data will be collected and verified, and the availability and quality of data for existing infrastructure will be assessed. This will involve the initial contact with these authorities to verify the availability of data and follow-up consultations to confirm the information and the potential environmental effects. A questionnaire will be developed to identify the existence of infrastructure such as water supply conduits, drainage works, culverts, pipelines, dykeland infrastructure (and associated farm land), landfills, and other public infrastructure (hydro and telephone lines). All record drawings, zoning maps, GIS information, aerial photography, existing survey pick up, field observation, maintenance and operating expenses and schedules, current emission and effluent volumes and characteristics which may be available for infrastructure located along the Petitcodiac River and its affected tributaries will be requested. Once all existing infrastructure components have been identified, they will be catalogued and assessed for application in the environmental effects analysis. At this point any remaining data gaps will be identified, and the means to fill the voids explored. The AMEC Team will consult with municipalities, health services and community services institutions to determine the status of existing municipal services that may be affected by the Project Options. Focus will be on emergency services due to the potential impediment of traffic flow during construction or operational maintenance. Data Sources
|
||||||||||||||||||||||||||||||||||||||||
|
The Petitcodiac River Causeway is an integral component of the GMA transportation network. The Town of Riverview has experienced considerable population growth since its completion. The Causeway provides a four-lane roadway connection between Moncton (Route 15 - Wheeler Blvd and Route 106 - Salisbury Road and Main Street) and Riverview (Route 112 - Coverdale Road and Route 114 - Hillsborough Road) and carries up to 30,000 vehicles and trucks per day. The alternate river crossing in the GMA at this time is the existing two-lane Gunningsville Bridge, which presently is operating near capacity. The Gunningsville Bridge is scheduled for demolition and replacement with a new four-lane bridge in the next few years. |
||||||||||||||||||||||||||||||||||||||||
|
Changes in Traffic Patterns |
||||||||||||||||||||||||||||||||||||||||
|
The continued use of the Causeway as it is at present (Status Quo), and the two Project Options that involve changes only to the operation of the Causeway fish gate, will not affect the transportation network. However, the Project Options that entail the replacement of segments of the Causeway with a new fishway or a new bridge will result in the temporary loss of River crossing capacity, and would necessitate the use of traffic detours during the construction phase. Operation of each Project Option may involve maintenance or operational activities that could affect the flow of traffic. During the construction phase, traffic may have to be rerouted to the planned new four-lane Petitcodiac River Bridge at Gunningsville and/or upriver to Salisbury to cross the River. This will increase traffic congestion and noise, as well as travel and vehicle operations time. Increased traffic along detour routes could lead to increases in vehicular accidents. Alternatively, the traffic could be retained along the Causeway routes through the construction of a temporary diversion structure, if found to be feasible. The spatial boundary of the road transportation network will be determined to encompass the potential traffic environmental effects area of the Project Options. This would include the alternate routes for travel between Riverview and Moncton. The temporal boundary will be limited to the construction phase of the project, as it is anticipated that upon completion of the Causeway reconstruction, traffic will return to the prior normal operating conditions. Temporal boundaries may include maintenance periods where traffic flow is potentially affected. Environmental effects on the road transportation network include the decline in traffic level-of-service, as well as the extent of potential highway safety, of the increased traffic generated and rerouted during the construction. In addition, environmental effects include the potential road infrastructure deterioration from additional truck traffic generated during construction. Medical and emergency services could also be affected during the construction period. The GMA traffic model will be used to simulate temporary traffic conditions during the construction phase of the Project Options involving installation of a new fishway or a bridge segment to the Causeway. The rerouted traffic will be compared to the existing traffic conditions to estimate the changes in traffic volumes, extent of travel delays and potential increase in vehicle accidents along the detour routes during construction. Once the selected Project Option is implemented, normal traffic conditions will return without any notable traffic network environmental effects. |
||||||||||||||||||||||||||||||||||||||||
|
Historically, the Causeway was a major addition to the GMA transportation network. Considerable residential growth in Riverview followed completion of the Causeway, which supplemented the cross-river highway capacity previously provided only by the Gunningsville Bridge. The past environmental effects since constructing the Causeway will be documented with respect to present traffic and population patterns in comparison with the pre-Causeway situation. This will characterise the cumulative environmental effects of past and present projects that will have overlapping environmental effects with those of the Project Options. The NBDOT presently has plans and is committed to replacing the existing two-lane Gunningsville Bridge with a new four-lane bridge at approximately the same location. Depending on the timing of the implementation of either of the two Project Options that entail modifications to the Causeway, the new Petitcodiac River Bridge could become an integral part of the traffic diversion plans during the construction phase. NBDOT will be consulted to confirm their plans, schedule and progress. The potential for other projects that will be carried out in the future that may affect the transportation network will also be identified and evaluated. Traffic induced by changes brought on by the Project Options (e.g., due to increased tourism or special events) will be assessed. |
||||||||||||||||||||||||||||||||||||||||
|
Mitigation in the context of the transportation network will be accomplished during the construction phase of the two Project Options that entail modifications to the Causeway through various traffic control measures. Traffic control measures may include alternate detour routings, installation of temporary traffic signals, signage, recommended staggered work hours, construction of a temporary diversion structure alongside the Causeway, etc. NBDOT and the GMA Municipalities will be consulted to discuss potential temporary construction phase traffic plans. Completion of a new Petitcodiac River Bridge in time to accommodate the diverted traffic during the construction phase of the Project Options would also provide a measure of mitigation. |
||||||||||||||||||||||||||||||||||||||||
|
Environmental Effects of the Causeway Environmental Effects of the Project Options Data Sources The net time, vehicle operations and accident costs will be estimated using the Transport Canada MicroBENCOST analysis model, or like methodology, and Provincial input cost parameters. Residual Data Requirements |
||||||||||||||||||||||||||||||||||||||||
|
The Causeway poses a barrier to vessel navigation and has also resulted in major changes to the River, both upstream and downstream. Vessel use on the River has also been affected by changes in technology, transportation requirements, the economy, demographics and recreational interests. The assessment of this component of the environment will need to examine both the physical changes in terms of vessel navigation as well as the resulting socio-economic environmental effects on transportation, fishing, tourism, and recreation. |
||||||||||||||||||||||||||||||||||||||||
|
Changes in Navigational Opportunities Navigation below the Causeway has been adversely affected by the siltation. Navigation, for most vessels is limited to the far field. This compares to pre-Causeway conditions where navigation, at high tide, was possible well beyond Moncton. Moncton, Salisbury and other communities were once very reliant on marine transportation, including boat building. However, developments of road, rail and air transportation have had dramatic changes on marine transportation in New Brunswick. By the time the Causeway was constructed there was no major freight transportation or boat building on the River. Since the construction of the Causeway, there has been a major expansion in recreational boating and fishing activity in the Province. The reduced navigation capabilities of the River, including the Causeway, have likely affected the potential for recreational boating use of the River. Thus, this component study will need to identify the environmental effects on the navigation capabilities (above and below the Causeway) of the Causeway, the Project Options and the cumulative environmental effects of other Projects including the Status Quo. Changes in Vessel Traffic |
||||||||||||||||||||||||||||||||||||||||
|
The hydrodynamic and sediment transport modelling work will provide an indication of river flows, width and depth of each Project Option. These will determine the environmental effects on navigation and vessel traffic on the River. The environmental effects of the Causeway will be determined by documenting navigation capabilities and vessel traffic prior to the Causeway construction, projecting what current navigation and vessel traffic would be today without the Causeway and comparing the two situations.
The cumulative environmental effects of each Project Option will be estimated by adding the environmental effects of the Causeway and the Option and comparing them to the pre-Causeway situation. The principal cumulative environmental effect of past projects is likely to have been the Status Quo. Understanding how the Status Quo has contributed to cumulative environmental effects on navigation will be important.
When the hydrodynamic and sediment transport modelling has determined the expected environmental effects on the navigation capabilities, potential mitigation options will be identified and assessed in terms of their environmental effect on both navigational capabilities and vessel traffic.
Environmental Effects of the Causeway
The pre-Causeway situation will be determined through reports and statistics available from Department of Fisheries and Oceans (DFO) (Canadian Coast Guard), NBAFA and municipal records. A number of interviews will also be conducted with individuals that were involved in commercial and recreational boating on the River prior to the Causeway and since. The current navigational capabilities and vessel traffic will be established through similar sources, including interviews. Current nautical charts and other navigational information will also be reviewed. Trends on both commercial and recreational vessel uses for New Brunswick will be examined to develop estimates of the environmental effects of the Causeway on vessel traffic. The difference between the current vessel traffic and the projected traffic (without the Causeway) will be used to determine the environmental effects on this component of the environment. Environmental Effects of the Project Options The levels, uses and types of vessel traffic will be documented. Current and former (pre-1967) levels of commercial vessel traffic data and navigation channels will be acquired for segments of the River below and above the Causeway, as available. Information on the potential environmental effects of the Causeway modification options on vessel traffic and navigation, and other related commercial activity will be discussed to establish what stakeholders perceive to be the nature and extent of environmental effects on their industries and activities. Data Sources It is expected that major information sources will be identified through referrals and contacts provided by:
The results of the other component studies will also be major information sources including, commercial fishery, recreation and tourism. |
||||||||||||||||||||||||||||||||||||||||
|
Archaeological and heritage resources (pre-European contact or post-European contact sites, structures, features and artifacts) are known to have existed along the banks of the Petitcodiac River and its tributaries, within the near, mid, and far field areas. The Archaeological Services Unit (ASU) and the Planning and Commemoration Section, Heritage Branch, of the Culture and Sport Secretariat are the agencies responsible for the identification, preservation, protection, and development of archaeological and heritage resources within New Brunswick. Project Options may cause changes to the environment, which could potentially affect archaeological and heritage resources. The requirement to consider archaeological and heritage resources is linked to the to the EIA process through Regulation 87-83 of the Clean Environment Act. Archaeological and heritage resources are considered to be non-renewable resources, and potential environmental effects resulting from Project Options must be considered. |
||||||||||||||||||||||||||||||||||||||||
|
Changes to Archaeological and Heritage Resources
Project environmental effects on archaeological and heritage resources are expected to be concentrated within the near field area, with some potential for extension into the mid- and far field areas. |
||||||||||||||||||||||||||||||||||||||||
|
Environmental Effects of the Causeway Maintaining the Status Quo may result in the continued deposition of sediments along the shoreline of the River. If these areas become stable over the long-term, it could result in increasing shoreline development, which may mean the disturbance of “original” shoreline areas that have a high potential to contain heritage resources. It is likely that construction of the Causeway resulted in the submergence of archaeological and heritage resources along the banks of the Petitcodiac River upstream of the Causeway, thus removing the potential for these sites to contribute to the shared heritage of all New Brunswickers. Environmental Effects of the Project Options Changes to archaeological and heritage resources could potentially occur during each of the Project Options. During construction, operations, maintenance and decommissioning activities, there could potentially be changes to the current and past shorelines both down and upstream of the current Causeway facility (to varying degrees). In addition, the potential environmental effects of the Project Options that result in the lowering of water levels in the head pond, listed below, could result in the exposure of archaeological sites which had been previously “protected” by vegetation. Opening the gates or installing a bridge will alter the present flow regime of the Petitcodiac River, potentially causing erosion of the riverbank, soil deposition, and the raising and lower of water levels, which could potentially affect archaeological and heritage resources. There may also be additional environmental effects to archaeological and heritage resources caused by construction activities associated with a bridge. In order to identify the anticipated Project Options environmental effects on archaeological and heritage resources, it will be necessary to identify the location of known archaeological and heritage resources within the potential zones of influence of the Project Options. A predictive modelling exercise to identify locations that exhibit an elevated potential for the recovery of previously unknown archaeology and heritage resources within the Potential zones of influence of the Project Options, will be undertaken. Once complete, the locations of known resources and elevated potential areas may be overlaid with results of the hydrodynamic and sediment transport modelling (for each Project Option) to identify locations of possible interaction. This evaluation will be based on the preliminary results of the hydrodynamic and sediment transport modelling. |
||||||||||||||||||||||||||||||||||||||||
|
Cumulative environmental effects arise where Project Options environmental effects overlap with past, present and future projects. The resultant environmental effects of the Project Options on archaeological and heritage resources may overlap with those of past projects, in that undoubtedly some of these resources have been lost as a result of past development and construction activities in the Moncton area. As a result of new federal and provincial legislation (e.g., the New Brunswick Environmental Impact Assessment process, Canadian Environmental Assessment Act), there is likely to be less environmental effect. These legislation seek to assess the potential environmental effects that present and future developments have on these resources, and by extension, require the implementation of mitigative measures. |
||||||||||||||||||||||||||||||||||||||||
|
Mitigative measures employed for archaeological and heritage resources largely depend on the significance of the resource to be affected, its location in relation to the Project Option activities being undertaken, and the severity of the potential environmental effect. Input from Archaeological Services Unit (ASU) and the Heritage Branch is key to the development of effective mitigative measures. Mitigation for archaeological and heritage resources can take a variety of forms, which may include, but are not limited to:
From a regulatory point-of-view, avoidance is always the preferred mitigation option. It will be necessary to develop Project Options and site-specific mitigation measures once a preliminary heritage evaluation has been undertaken, and known and potential resources have been identified. |
||||||||||||||||||||||||||||||||||||||||
|
Environmental Effects of the Causeway
Residual Data Requirements Locations where the “original” shoreline could be affected by erosion, and deposition, as a result of the Project Options and Status Quo, will be subject to the archaeological modelling exercise. Unless there is zero potential (due to extreme ground disturbance, for example), then confirmatory fieldwork will be undertaken at locations using standard archaeological techniques. The scope of work required to fill the residual data requirements will be somewhat dependent on the results of the hydrodynamic and sediment transportation modelling. However, it is anticipated that all locations with known resources and areas exhibiting high archaeological potential, as well as, a representative sample of medium and low potential areas that may be affected by any of the Project Options will be subjected to a preliminary surficial survey. Heritage resources encountered during the preliminary survey will be evaluated and assessed for significance. The intent of the preliminary survey will be to determine the location and extent of the archaeological and heritage sites, identify the potential environmental effects of each option, and determine what mitigation is required. If required, a detailed evaluation may be recommended if existing, or potential archaeological and heritage resources are identified and Project Option environmental effects are unavoidable. Pre-fieldwork studies (document review) will be completed in spring 2003. Environmental Effects of the Project Options Mitigation Options In general, it is likely that the Heritage Resource Evaluation of the Project Options will contribute to the archaeological and heritage knowledge base of the study area through the development of an archaeological and historical profile of the area, and the identification of previously unknown archaeological and heritage resources and areas exhibiting an elevated potential for the recovery of additional resources. With the development of proper mitigation measures, it is unlikely that the Project Options will result in significant adverse environmental effects to archaeological and heritage resources. However, if archaeological and heritage resources are to be affected by the Project Options, it may be possible in some situations to offset the loss through compensation-in-kind. For heritage resources, this includes a wide variety of potential public-oriented heritage programs (i.e., investigative projects, site conservation, site commemoration, etc.). Due to the unique nature of some components of these resources (e.g., pre-contact archaeological sites), there will likely need to be a graded compensation evaluation and compensation may not always be appropriate or possible. It should be noted that compensation is the last resort, and can only be considered once all potential mitigative options have been exhausted. Data Sources
|
||||||||||||||||||||||||||||||||||||||||
|
Tourism is big business in New Brunswick. Total tourism expenditures in the province reached $1.2 billion in 2002, making it the most successful year in the province’s tourism history. The economic environmental effect of this sector is significant, maintaining an estimated 33,000 person years of employment and generating $295 million in tax revenues ($162 million in federal taxes; $89 million in provincial taxes and $44 million in municipal receipts). A record 2 million people visited the province in 2002. The largest share, 26%, was from the Maritime Region, followed by the U.S. with 24% and Ontario and Quebec with 23% and 22% respectively. Annual occupancy rate for accommodations averaged 56% for 2002, climbing to 80.5% for the peak months of July and August. Room sale revenues increased 12.4% over 2001 to more than $160 million. Attendance at attractions varied across the province with combined attendance at leading provincially or federally supported attractions totalling over 1 million visitors for the peak season of May to October, an increase of nearly 7% over 2001. The Petitcodiac River, head pond and shore areas have and continue to provide major tourism opportunities for non-resident and resident visitors. The Causeway has resulted in major physical changes creating both positive and adverse environmental effects on local and regional tourism activities. Implementation of the Project Option(s) may result in physical changes to the river system (including head pond) and biophysical changes to habitat and characteristics (migration patterns) for important tourism related species (birding, wildlife observation, angling, etc.), which may affect tourism opportunities. This component study will examine the environmental effects of the Project Option(s) in terms of historical, current and potential future tourism activities and interests.
Potential Effects on Existing Tourism Opportunities
New and/or Enhanced Tourism Opportunities Non-Resident and Resident Visitor Tourism Interests and Preference |
||||||||||||||||||||||||||||||||||||||||
|
Environmental effects of the Causeway Environmental Effects of Project Options Since 1968, there have been significant changes in demographics, technology, values and interests in the tourism sector. Consequently, there are associated major changes in how the Study Area is or would have been used for tourism. |
||||||||||||||||||||||||||||||||||||||||
|
The cumulative environmental effects of each Project Option combined with other projects in the region will be examined. The process will entail overlaying the tourism related environmental effects of the other projects with the potential tourism environmental effects of the Petitcodiac River Causeway Project Options, and determining whether there would be a positive synergistic environmental effect or an adverse conflicting environmental effect.
The anticipated tourism environmental effects will be enhanced (positive environmental effects) or reduced/eliminated (adverse environmental effects) through the identification of optimization and mitigation measures. Mitigation options could include introduction/enhancement of tourism opportunities in other locations or improving access or use of unaffected tourism opportunities within the Study Area.
Environmental Effects of the Causeway Current and pre-Causeway tourism opportunities and levels of activity will be documented, including:
Key stakeholders will be interviewed to attempt to characterise pre-Causeway tourism, especially activities such as fishing in the headwaters, discontinued festivals, and tourism-related recreational activities. Environmental Effects of Project Options
Mitigation Options
Data Sources Tourism visitation and activities statistics within region (NBTAP, BNB, CEDA). Relevant tourism and demographic data from Statistics Canada, Canadian Tourism Commission, World Tourism Organization. Interviews with key informants about pre-Causeway tourism and recreational activities, especially in the headwaters. |
||||||||||||||||||||||||||||||||||||||||
|
The Petitcodiac River, head pond and shore areas have and continue to provide major recreation opportunities for residents and visitors. The Causeway has resulted in major physical changes resulting in both positive and adverse environmental effects on marine and shore based recreation. The Project Options are intended to reverse some of the environmental effects of the Causeway, which may further affect the recreation opportunities. This component study will need to examine the physical environmental effects of the Causeway and the Project Options in terms of historical and current recreational activities and interests. |
||||||||||||||||||||||||||||||||||||||||
|
Changes to Existing Recreation Opportunities Community and Visitor Recreational Interests and Preference |
||||||||||||||||||||||||||||||||||||||||
|
Environmental Effects of the Causeway The first task will be the documentation of the recreational activities along River prior to Causeway construction. The anticipated information sources will be various municipal and provincial reports, photographs and personal interviews with key informants, especially in the headwaters, above the Causeway. The current recreational activities will then be documented through existing reports and data supplemented by interviews with municipal, provincial and recreation organizations. A comparison of the before and current recreation situations will identify the changes in recreational opportunities and levels of activity. The final task will be to assess the changing recreational needs and interests through a review of local recreation reports and plans, literature search and interviews with municipal and provincial recreation officials as well as a review of demographic information. Environmental Effects of Project Options The Project Options will be assessed as to their environmental effect on the head pond, River, tidal action and shoreline in terms of enhancing or detracting from recreational opportunities. Short term and long-term environmental effects on recreational activity levels will be estimated for each alternative based on current activity, trends in recreation activities, expected changes in recreational opportunities, regional recreation plans and strategies. |
||||||||||||||||||||||||||||||||||||||||
|
Each alternative will be examined in terms of the cumulative environmental effects of the Project Options and the Causeway. The process will entail combining the Causeway and Project Option environmental effects in terms of recreational opportunities along with the assessment of the changing recreational interests and requirements. The changes in recreational interests and requirements are significant since 1968. Changing demographics, technology, values and interests have resulted in major changes in how the Study Area is or would have been used for recreation. These overall changes in recreation will be combined with the environmental changes that have occurred as well as the anticipated changes due to each Project Option.
Review of existing recreation activities and interests will include the identification of opportunities for enhancement through mitigation measures. These could include modifications to the Status Quo and the Project Options. Other mitigation options could include enhancement of recreation opportunities in other locations or improving access or use of unaffected recreational opportunities within the Study Area.
Environmental Effects of the Causeway
Environmental Effects of Project Options
Mitigation Options
Data Sources Recreational Fishing Statistics and Licenses of Area. (NBAFA, NBTAP, NBCSS). Inventory of Tourism Activities Along River and Shoreline - Baseline and Pre-1967. (NBTAP, NBCSS, BNB). Interviews with agencies and key informants identified in scoping. Tourism Visitation and Activities Statistics within Study Area. (NBTAP, BNB). Inventory of Recreational Boating and Commercial Vessel Activities and Traffic along River - Baseline and Pre-1967. (NBAFA, NBTAP, NBCSS). Current and Pre-Causeway Provincial and Regional Recreation Reports. River and Estuary Fisheries Catch and Value. (NBAFA). Statistics Canada Demographic Data. Fisheries, Tourism, and Vessel Traffic and Navigation Component Studies. |
||||||||||||||||||||||||||||||||||||||||
|
The construction, operation and decommissioning of the Project Options and Status Quo have potential environmental effects on public health and safety. These arise primarily from project-related potential accidents or through project-related changes in the environment that may have implications for public health and safety (e.g., changes in groundwater quality or release of contaminants). A number of public health and safety issues have been raised in the EA Guidelines.
Vehicular Accidents Non-Vehicular Accidents Quality and Quantity of Groundwater Contaminated Effluents Human Disease Vectors Flooding Re-Distribution of Contaminants |
||||||||||||||||||||||||||||||||||||||||
|
The potential environmental effects of the Project Options and the Status Quo include the following as per the discussion of issues and concern in Section 2.9.2:
|
||||||||||||||||||||||||||||||||||||||||
|
Various past, present and future projects may have cumulative environmental effects on public health and safety that overlap with those of Project Options. These other projects have/do/will result in vehicle and non-vehicle accidents. Various activities affect groundwater quality and quantity in the aquifers adjacent to the head pond. Other projects may be affecting the presence and distribution of human disease vectors. The current projects do affect to some extent, accident rates related to recreational activities. There are flood risks associated with other projects that may overlap with those associated with the Project Options. Some past and present projects may result in cumulative environmental effects on human food resources (e.g., uptake of contaminants). |
||||||||||||||||||||||||||||||||||||||||
|
Mitigation of vehicle accidents related to Project Options will be addressed through the Transportation Network (Section 2.4). Measures include various traffic management and safety procedures for diversions around work areas and other measures that reduce peak traffic flows. Non-vehicular accident mitigation would be related primarily to tourism and recreational activities. These could be mitigated through signage, public awareness, and operator safety procedures. Changes in groundwater resources could be mitigated through a range of potential measures including change in well construction, monitoring, and planning of water withdrawal. This will depend upon potential environmental effects, if identified through the environmental effects analysis. Changes in water quality that are mitigable would include particular measures such as protection of the closed Moncton landfill. Re-distribution of existing municipal effluents may be difficult to mitigate. These measures would be similar for food resource harvesting of contaminated plants and animals. Flood risk mitigation would be related to engineering design measures that ensure structure capacity and integrity meet anticipated ranges of natural events without failure. |
||||||||||||||||||||||||||||||||||||||||
|
Environmental Effects of the Causeway and Project Options Non-vehicle accidents will be obtained from various data sources and interviews of recreational and tourism operators and users. Potential groundwater impacts will be evaluated using available data regarding wells and hydrogeology in the areas adjacent to the head pond. Professional judgement models will be used to evaluate the potential for groundwater quantity and quality related environmental effects. Change in recreational water quality will be predicted using the water quality modelling from the hydrodynamic and sediment transport modelling studies. Change in vectors (e.g., mosquitoes and rodents) will be estimated qualitatively by noting Project Option related changes in habitat. Change in flood risk will be evaluated qualitatively based on engineering design considerations based upon the current design of infrastructure and the design of Project Options. Change in human food resources will be determined by establishing where, and what food resources are harvested within the zones of influence of Project Options. Water quality modelling will assist in evaluating the extent to which there may be changes in contaminant distribution levels in areas of food resource harvesting. Data Sources Residual Data Requirements The principal residual data requirements include:
|
||||||||||||||||||||||||||||||||||||||||
Questions or comments regarding this site should be directed to: Sherry Sparks - Environmental Impact Assessment Manager, © 2003 All rights reserved. |